Zambia National Contingency Plan for Floods
颁布于 2008-11 · 文本截至 2026-10-01
以研究形式发布的公开法律与官方指引,不构成法律、税务或金融建议。
研究内容本身以英文撰写。标题和标签已翻译,调查结果和引文未翻译。
关于这部法律
- 语言
- English
- 类型
- policy
- 组织
- Zambezi Watercourse Commission (ZAMCOM)
- 国家
- 赞比亚
- 主题
- Environment, Food and nutrition, Water, Waste and hazardous substances
- 关键词
- protection of environment, flood, public health, risk assessment/management, water shortage/drought, hazards, food security, education, meteorology, hygiene/sanitary procedures, waste disposal, waste management
在哪里阅读
文本
所收录的法律原文,按条款排列。每个条款都有自己的链接。
2008/09 ZAMBIA NATIONAL CONTIGENCY PLAN i Country: Zambia Date: November, 2008 Period: October 2008 – June 2009 Zambia National Contingency Plan for Floods Property of the Republic of Zambia Disaster Management and Mitigation Unit of the Office of the Vice President P.O Box 54689, Lusaka Zambia Tel: +260-21-1-252692/253123 e-mail: dmmu-ovp@zamnet.zm ii Table of Contents Acknowledgements --------------------------------------------------------------------------------------------------- iii Executive Summary ---------------------------------------------------------------------------------------------------iv Preamble------------------------------------------------------------------------------------------------------------------vi 1.0. INTRODUCTION------------------------------------------------------------------------------------------------ 1 2.0. CONTEXT, HAZARDS AND RISK ANALYSIS --------------------------------------------------------------- 2 2.1. Context------------------------------------------------------------------------------------------------------------- 2 2.2.1. Floods ------------------------------------------------------------------------------------------------------- 3 2.3. Risk Analysis --------------------------------------------------------------------------------------------------- 5 3.0. SCENARIOS AND PLANNING ASSUMPTIONS--------------------------------------------------------------- 5 3.1. Scenario ----------------------------------------------------------------------------------------------------------- 6 4.0 PROPOSED PREPAREDNESS, RESPONSE AND REHABILITATION ACTIVITIES (SECTOR BY SECTOR) -------------------------------------------------------------------------------------------------------------- 7 4.1. Objective ---------------------------------------------------------------------------------------------------- 7 4.2. Strategy ------------------------------------------------------------------------------------------------------- 7 4.2.1. Capacity Building------------------------------------------------------------------------------------ 7 4.2.2. Response ----------------------------------------------------------------------------------------------- 7 4.2.3. Early Warning/Information Flow ----------------------------------------------------------------- 7 4.3. Guiding Principles ---------------------------------------------------------------------------------------- 7 4.4. Preparedness Activities--------------------------------------------------------------------------------- 8 5.0. RESOURCE GAP ANALYSIS------------------------------------------------------------------------------------- 8 6.0. Management and Coordination Arrangements----------------------------------------------------- 9 7.0. Roles and Responsibilities-------------------------------------------------------------------------------10 8.0 Resource Mobilisation-------------------------------------------------------------------------------------13 9.0. RAPID ASSESSMENTS AND DISSEMINATION OF INFORMATION-----------------------------------13 10.0 ANNEXES ---------------------------------------------------------------------------------------------------------14 Annex 1: Road Infrastructure Sector --------------------------------------------------------------------------15 Annex 2: Human Settlement and Shelter Sector-----------------------------------------------------------34 Annex 3: Health and Nutrition -----------------------------------------------------------------------------------40 Annex 4: Water and Sanitation----------------------------------------------------------------------------------45 Annex 5: Education---------------------------------------------------------------------------------------------------50 Annex 6: Agriculture and Food Security Sector------------------------------------------------------------53 Annex 7: Information Management and Emergency Communications -----------------------------59 Annex 8: Logistics ----------------------------------------------------------------------------------------------------64 Annex 9: Detailed Sector Resource Gap Analysis ---------------------------------------------------------66 Annex 10: Disaster Risk Reduction (DRR) Sector Focal Point Persons-----------------------------71 iii Acknowledgements Disaster Management and Mitigation Unit (DMMU) wishes to acknowledge the following institutions and organisations for their contribution towards the preparation of this contingency plan: • Communications Authority of Zambia • Department of Water Affairs • Department of Resettlement • Food Reserve Agency • OXFAM • Ministry of Health • Ministry of Agriculture and Cooperatives • Ministry of Education • Road Development Agency • United Nations Country Team • Zambia Red Cross Society iv Executive Summary This contingency plan covers the planned activities to be undertaken in 2008/09 rainy season with scenarios for the likely occurrence of floods based on the Zambia Meteorological Department (ZMD) rainfall forecasts. The 2008/09 rainfall forecast has revealed that most parts of the country will receive normal to above rainfall between October and December 2008 with the exception of north-eastern parts of the country (Nyika plateau area comprising of Nakonde, Isoka and Lundazi) which are expected to receive normal to below normal rainfall during the same period. However, it is anticipated that during the period from January to March 2009, the whole country is expected to receive normal to above normal rainfall. Based on previous experience, the occurrence of above normal rainfall may precipitate the occurrence of excessive rainfall or flash floods in low lying areas of the country. The Contingency Plan draws on historical data and experiences of the occurrence of disasters such as floods and/or dry spells as a building block for coming up with planning assumptions and likely scenarios should such hazards occur during the 2008/09 rain season. The overall objective of the Contingency Plan (NCP) is to support the timely, consistent and coordinated response to anticipated floods in the 2008/09 rainy season, thus effectively minimising the impact of the floods on human population, livelihoods, lifelines and the environment. This will in turn help reduce the scale of humanitarian needs to the affected population. Although the emphasis of the plan is on floods, the plan has an in – built flexibility that allows it to embrace other hazards such as drought and cholera should they occur anywhere in the country. The contingency plan shall be implemented at three stages i.e. before the emergency, during and after. Preparedness activities before the emergency are informed by sector response plans in annexes 1-8. The sectors covered in the contingency plan are Human Settlement and Shelter, Health and Nutrition, Water and Sanitation, Education, Agriculture and Food Security, Public Infrastructure, Information Management and Emergency Communication. Scenario analysis and assumptions are the main determining factors responsible for the scope and depth of the contingency plan. In order to ensure a coordinated response, guidance is provided on who should carry out rapid assessments and later on disseminate the related information. In the same vein, participation of all our cooperating partners and stakeholders are maximised in the plan by encouraging them to isolate activities whose implementation they are in a position to support. v The total budget for the implementation of the contingency plan is K98,984,267,855.00 (US$21,996,503.97) broken down as shown in the table below: No Name of Sector Number of Activities Net financial requirements (ZMK) Net Financial requirements (US$) @ K4500 1 Infrastructure 6 10,400,000,000.00 2,311,111.11 2 Human Settlement and Shelter 13 2,172,656,817.00 482,812.63 3 Health and Nutrition 8 1,040,608,332.00 231,246.30 4 Water and Sanitation 18 14,362,000,000.00 3,191,555.56 5 Education 16 6,930,000,000.00 1,540,000.00 6 Agriculture and Food Security 11 40,099,134,356.00 8,910,918.75 7 Information Management and Emergency Communication 4 663,983,550.00 147,551.90 8 Logistics 3 23,315,884,800.00 5,181,307.73 GRAND TOTAL 98,984,267,855.00 21,996,503.97 vi Preamble This contingency plan is a follow-up to the 2007/8 contingency plan. It covers a floods scenario. The main objective of the contingency plan is to reduce the impact of floods on the affected population by creating a framework for providing the basic humanitarian needs to the affected population. The basic assumption behind the plan is that the sectors likely to be affected are public infrastructure i.e. roads, schools, bridges. Other sectors are health and nutrition, water and sanitation, agriculture and food security, human shelter and settlement and education. The contingency plan is premised on the following: The interventions’ fundamental objective is to minimize in the first instance loss of human lives and secondly the minimal loss to livelihoods. This objective is broken down to sector based objectives. Among the strategies is to ensure that the institutions such as Department of Water Affairs in the case of floods will provide water level information updates to the Disaster Management and Mitigation Unit (DMMU). This will be done together with the Zambia Meteorological Department (ZMD) which will monitor the rain intensity especially in the flood prone areas. At the same time the Ministry of Health Diseases Surveillance Unit will monitor actively any potential cholera threats and outbreaks especially in fishing camps, markets and streets where open air food stalls are usually located. The roadside stalls are a major source of outbreaks as they are located in hygienically compromised areas. The contingency plan will be managed by the Office of the Vice President through the Disaster Management and Mitigation Unit (DMMU), with support from other partners in the Disaster Management Consultative forum (DMCF). The DMCF which is co-chaired by the Government and the United Nations will be used to make decisions at policy level as well as serve as an information sharing platform before, during and after the crisis. The frequency of meetings will be determined by the severity of the crisis and the capacity by Government to handle the crisis. At technical level the Zambia Vulnerability Assessment Committee (ZVAC) under the DMMU will meet regularly to ensure that information is flowing and the ZVAC members will in turn inform their principals who sit in the DMCF. All public information relating to the crisis will be disseminated by the Government through the Disaster Management and Mitigation Unit (DMMU). The Emergency Operations Center (EOC) located at the DMMU will serve as the data center from where all information shall be received and analysed. The information will be sent to DMMU through the District Disaster Management Committee (DDMC) and verified by the District Commissioner who chairs the DDMC. In terms of response, most of the prone areas are in rural areas where there is limited public infrastructure such as roads, warehousing and bridges. This will form the major constraints in terms of access. The lack of stand by human and financial resources will also form a constraint for the operational response. There is likely to be constraints in terms of the right type of transport which will need to have amphibious capacity especially if the affected areas are cut off by water. Communication by whatever means is also likely to be a constraint especially in getting information from the affected areas. 1 1.0. INTRODUCTION This contingency plan covers the 2008/09 rainy season with scenarios for the likely situation based on the SARCOF and Zambia Meteorological Department (ZMD) rainfall forecasts. The 2008/09 rainfall forecast has revealed that most parts of the country will receive normal rainfall between October and December 2008 with the exception of north-eastern parts of the country (Nyika plateau area comprising of Nakonde, Isoka and Lundazi) which are expected to receive normal to below normal rainfall during the same period. However, it is anticipated that during the period from January to March 2009, the whole country is expected to receive normal to above normal rainfall. The Contingency Plan uses the most-likely scenario in coming up with the figures used in the document. The Plan also draws on historical data and experiences of the occurrence of disasters such as floods and/or dry spells as a building block for coming up with planning assumptions and likely scenarios should such hazards occur during the 2008/09 rain season. The overall objective of the Zambia National Contingency Plan (NCP) is to support the timely, consistent and coordinated response to anticipated floods in the 2008/09 rainy season, thus effectively minimising the impact of the floods on human population, livelihoods, lifelines and the environment. This will in turn help reduce the scale of humanitarian needs to the affected population. The Plan also has an in – built flexibility that allows it to embrace other hazards such as drought and cholera should they occur anywhere in the country. The specific objectives the NCP aims at addressing are as follows: i. To improve the management and coordination of preparedness, response and rehabilitation arrangements ii. To improve early warning information sharing to ensure effective response. iii. To ensure timely resource mobilization and response iv. To reduce the risk of secondary hazards i.e. epidemics v. To ascertain the sector based level of impact of floods vi. To ascertain the type and quantities of assistance to be required as a result of the emergency vii. To identify and define roles and responsibilities of all partners in emergency response viii. To utilise emergency and recovery assistance as baselines towards building long term interventions Identification of the geographical areas likely to be affected by floods during the 2008/09 season used a spatial and buffer analysis of the main river systems and perennial wetland areas elevation information embedded within the agro-ecological zones. It is anticipated that a total of 31districts are likely be affected by floods. These are Chavuma, Kabompo, Mwinilunga, Solwezi and Zambezi (North Western province), Mongu, Senanga, Kalabo, Lukulu, Sesheke, Shang’ombo (Western Province), Samfya (Luapula), Kazungula, Namwala, Itezhi Tezhi, Siavonga, Monze, Mazabuka, Sinazongwe and Gwembe (Southern Province), Serenje and Mkushi [Central Province] as well as Kafue, Luangwa, and Lusaka [Lusaka Province]. The contingency plan is premised on the following assumptions: � All the stakeholders realize that the contingency plan and its implementation is the responsibility of everyone and shall therefore be implemented by all stakeholders by partnering with sectors that relate to their core functions. This will be done under the coordination of the Disaster Management and Mitigation Unit (DMMU). 2 � The Office of the Vice President (OVP) through DMMU will coordinate the implementation of this contingency plan. The Plan will be implemented through the implementing partners who include Government line Ministries, local and international NGOs and the United Nations Country Team (UNCT). � DMMU will coordinate all matters related to the emergency and will ensure that all stakeholders are informed of what is happening through the National Disaster Management Consultative Forum (NDMCF) and the media. � The Emergency Operations Centre (EOC) located at the DMMU will serve as the data centre from where all information shall be received and analysed. The information will be sent to the districts through the District Disaster Management Committee (DDMC). The data to be received and analysed at the EOC will include data on water levels which shall be provided by the Department of Water Affairs/Zambezi River Authority and ZESCO. Rainfall data will be provided by the Zambia Meteorological Department (ZMD) while that of affected populations will be provided by the DDMC and verified by the Zambia Vulnerability Assessment Committee (ZamVAC) through Rapid Assessments. It is anticipated that all information pertaining to the emergency shall be cleared by Government through DMMU before being disseminated. � The various coordination fora such the Inter Agency Standing Committee (IASC) of the United Nations and IFRC, and the INGO forum will continue to play their important role with a view of complimenting the national coordinating mechanism. � This Contingency Plan will endeavour to minimize the impact of the disasters for which it has been designed to avert the loss of lives and livelihoods. All the minimum assistance to be provided to the affected populations will be given through DMMU. � Interventions proposed shall not erode the normal livelihoods of the affected population but shall instead help to build on them. 2.0. CONTEXT, HAZARDS AND RISK ANALYSIS 2.1. Context Zambia has an estimated population of 12.5 million1 people of which 65% live in rural areas. The majority of the rural population depend on subsistence agriculture as their source of livelihood. About 58 percent of Zambia’s total land area of 39 million hectares is classified as having medium to high potential for agricultural production, but less than half of potential arable land is cultivated. The most popular type of farming practiced by these farmers is mixed farming. The majority of subsistence farmers in Zambia grow rain fed crops particularly maize, which is the main staple food crop. Other major crops include millet, sorghum, cassava and rice. The Living Conditions Monitoring Survey of 2006 states that national poverty stands at 64% with rural poverty at 80% making the rural population extremely vulnerable to disasters. This vulnerability coupled with frequent occurrence of hazards makes populations in rural areas more at risk. In the 90s the country experienced climate related crises with a drought in 1991/92. There was widespread hunger due to these droughts that affected most countries in Southern Africa. Another major drought hit Zambia in 2001/02 which even led to a consolidated appeal process 1 Population Projects Report 2000, CSO 3 (CAP). This drought affected about 2.4 million2 people mostly in rural areas where their livelihoods depend on agriculture. These droughts affected the crops which are rain fed as they could not mature. This led to wide spread hunger in the whole country. In 2006/07 the traditional flood prone areas of North western and western Zambia experienced floods. The floods impacted on infrastructure i.e. roads, schools, habitation, agriculture, water and sanitation. Furthermore, the 2007/08 floods started earlier than anticipated affecting the southern half (low lying areas and major river basins) of the country. According to Zambia Meteorological Department forecast for the 2008/09 rain season, the greater part of Zambia is forecast to have normal to above normal rainfall from October to December except for the north-eastern parts of the country (Nyika Plateau, Chama and Lundazi) which will experience normal to below normal rainfall. During the period from January 09 to March 09, the whole country will receive normal to above normal rainfall. The context of emergencies in Zambia usually has a multi-sectoral impact hence the need for wider planning approaches. The impact of floods on the population is likely to be exacerbated by the rising food prices especially in districts which were adversely affected during the 2007/08 season. As people’s resilience levels get eroded, they will resort to other unsustainable means such as risky sexual behaviour in exchange for money and essentials. This may lead to vices such as exploitation and abuse. Some engage violent means in order to suppress the vulnerable populations. This may in turn lead to high occurrence of gender based violence. 2.2. Hazards 2.2.1. Floods Taxonomy Disasters that are associated with flood hazards in Zambia have been caused by the bursting of river banks due to heavy and high intensity rainfall. Furthermore, over utilisation of the wetland areas has the potential to create environmental degradation which may negatively impact on the entire ecosystem. The untimely release of excess water from Kariba, Itezhi Tezhi, Kafue Gorge Dams on Zambezi and Kafue Rivers respectively, will have devastating effects downstream. Due to poor drainage systems in urban districts within the unplanned settlements, there were cases of urban flooding during the 2007/08 rain season. This was common in Lusaka, Central and Copperbelt Provinces respectively. It is worth noting that 2006/07 and 2007/08 seasons exhibited diverse and varying characteristics (in terms of flood scenarios) which resulted into severe flooding that heavily impacted on several sectors. Furthermore, these rains started and intensified earlier than expected catching most populations residing in areas that periodically don’t flood seasonally unaware (Zambezi and Luangwa Rift Valley Areas).. Following the 2008/09 rainfall forecast from the Zambia Metrological Department indicating that the country will experience normal to above normal rainfall, there is a higher probability of floods occurring. Impact In the event of floods, the following are the sectors which are likely to be affected: 2 Food Needs in-depth Assessment 2002 4 Human Settlement and Shelter Populations living within the 5 km buffer from the main river systems and wetlands will lose their dwellings either due to high levels of water or structures collapsing due to excess rainfall. Most of the dwellings are built of poor quality building materials and are susceptible to flood damages. Health and Nutrition Due to flood waters, there is an increased risk of malaria, waterborne diseases (Cholera), hygiene related diseases (Dysentery), and Acute Respiratory Infections as a result of exposure. Snakes, rodents and other insects may retreat to the same dry areas as the human population, resulting in further risk of snakebites, plague and other related risks. Populations may have limited access to health facilities due to damages on road and health infrastructure. This will to a larger extent affect stocking levels of medical supplies (e.g. medicines, cold chains) and will particularly impact on important programmes such as ART. In addition, there is risk of increased malnutrition among the under five children due to lack of food for supplementary feeding Water and Sanitation There is a high risk of water contamination of drinking water due to flooding of sanitation facilities such as latrines and septic tanks. Affected populations will therefore be rendered susceptible to various water borne diseases i.e. cholera, dysentery and hygiene related diseases (scabies and other skin diseases). There is also a high risk of lack of clean water for household chores such as cooking and cleaning Education When flooding occurs when the school calendar is just beginning or midway through the first term, there is a risk of school children missing out on a major part of the curriculum. There is also a likelihood of some pupils not being able to attend school as they may be cut off due to floodwaters and damaged infrastructure. Pupils may also be cut off as a result of the families being completely displaced due to damages to their habitations. In some instances displaced populations, including school teachers, may occupy school buildings as emergency shelter forcing temporary closure of the schools that might otherwise be on highland and not directly affected by the emergency. Agriculture and Food Security Most of the food stocks for consumption are kept either in the dwellings or in grain bins that may have been submerged or damaged by rainfall or flood waters. Existing planted crops may be submerged or washed away resulting to total loss and/or decreased yield. Flooding of crop fields may cause the farmers to plant new crops. This may result into reduced yield due to loss of germplasm of adapted traditional varieties as well as decreased soil productivity due to loss of micronutrients that would have been washed away. In addition to direct loss of livestock in flood affected areas, there is also a risk of an increase in livestock diseases due to movement from the flood affected areas. There are at the same time positive aspect, usually when flood water recedes as there is residual matter that is deposited. Infrastructure There is a risk of flood affected areas becoming inaccessible due to basic support infrastructure such as boreholes, culverts, bridges and sections of roads being washed away. There is also the risk of communication infrastructure either being submerged in water, or damaged by hailstorms. There is also a potential of disrupting electricity supply which may cause high voltage electrocution where the areas affected are near high voltage electricity carrying pylons. 5 Cross Cutting Issues Because of the nature of emergencies, issues relating to violation of human rights and protection are either not taken into account or are left till the end when they would have gone out of hand. Though according to the two previous emergencies, there has been no report of such incidences. These issues include gender based violence (GBV), sexual exploitation, sexual and child abuse. Sexual abuse will also lead to rising incidences of HIV and AIDS. It is therefore important to ensure that during the planning stages, these issues are taken into account to avoid the risk of occurrence. 2.3. Risk Analysis The most likely emergency to befall the country are the floods which are likely to occur during the 2008/09 rainy season. In planning for the scenarios identified in each of the sectors, risk analysis was undertaken based on historical rainfall data for past flood years (2006/07 and 2007/08 seasons), spatial data analysis on the main river systems and perennial wetland areas, elevation information embedded within the agro-ecological zones. Furthermore, current and updated sector specific data was also used. Spatial and risk analysis was done using ARCVIEW GIS to develop risk maps of potential flood affected areas. 3.0. SCENARIOS AND PLANNING ASSUMPTIONS This plan is developed to address floods as this is the most likely emergency that the country will deal with during the coming rainy season. Floods tend to cause multiple impacts on infrastructure, Education, Health, Water and Sanitation and Agriculture. Table 1: Risk Analysis Table for Floods Type of Hazard Floods Likelihood Almost certain Magnitude High (North Western & Western) Moderate (Luapula, Eastern and Central) High (Southern) Impact Medium for most locations on Infrastructure, health, food security, water and sanitation, generally on livelihoods and education. Location and Geographical Area Eastern Province (Mambwe, Chama and Lundazi), N-Western province (Kabompo, Zambezi, Chavuma, Mwinilunga, Solwezi); Western province (Mongu, Senanga, Kalabo, Lukulu, Sesheke, Shang’ombo); Luapula province (Samfya) Southern Province (Kazungula, Namwala, Itezhi-tezhi, Siavonga, Sinazongwe, Monze, Mazabuka and Gwembe), Lusaka Province ( Kafue, Luangwa, Lusaka), Copperbelt Province (Kitwe and Ndola), Central Province (Kapiri Mposhi, Mkushi and Serenje) Triggers High levels of rainfall, the intensity of rainfall, rising water levels in the river basins mentioned above, rate of drainage, animal movements such as snakes, rats into human habitations, Water springing from the ground Time Frame October 2008 – June 2009 6 3.1. Scenario Based on the spatial and risk analysis, the following was the most likely scenario to unfold should floods occur during the coming rainy season: Hazard (Floods) Effect Most Likely The effect of the 2008/09 floods is likely to range from moderate to high in most parts of the country. 50 to 70% of the households residing within flood prone areas (i.e. 5 km buffer from the main river systems and perennial wetlands) will be adversely affected. In Health sector, 546,045 people (91,008 households) are likely to be affected by floods from sixteen (16) out of 31 districts. It is also assumed that some of these affected persons will completely be displaced and will access health services from nearby health facility. In Water and Sanitation sector, 475,823 people are likely to be affected in thirty one (31) districts. Out of 475,823, it is assumed that the 19,033 persons will completely be displaced and will require temporal shelter. This entails that water and sanitation services for the displaced will be required during and after the flood episode. In Agriculture and Food Security sector, it is anticipated that 699,678 persons in 27 Districts will be in need of food relief amounting to 27,988 MT of cereals for the period of five (5) months starting from December 2008 to April 2009. These are mainly populations whose fields and general livelihood sources will be affected by floods. This also takes into consideration the aspect of rising food prices which will exacerbate the already flood impacted population residing in the urban districts identified as being at risk of floods. In Infrastructure sector, it is assumed that all the thirty-one (31) districts which will be affected by the 2008/09 floods will experience infrastructure damage in one way or another. It is anticipated that flooding will cause damage to road embankments and drainage structures such as bridges, culverts and other river crossings respectively. The main priority will be to provide technical assistance and ensure that stop-gap measures are put in place to guarantee accessibility and swift return to normality. Priority will also be given to feeder roads which are likely to be affected and crossings leading to essential facilities such as markets, clinics and schools. In Human Settlement and Shelter sector, it is anticipated that 15,972 persons (2,662 households) will be displaced and will need temporal shelter and other essential household items. In Education sector it is anticipated that 374 schools in 28 districts will be affected by the floods. The schools will require temporary learning facilities and materials in order to continue functioning during the period of the floods. Government will facilitate relocating populations residing in perennial flood prone areas to higher grounds depending on the level of willingness. This will involve identification of suitable sites and providing these sites with basic infrastructure such as roads, bridges, latrines, health and education facilities. Households will be provided with the Non Food Items (NFIs) such as sleeping mats, blankets, 7 Hazard (Floods) Effect mosquito nets, water containers, cooking utensils and charcoal. In addition households will be provided with relief food. 4.0 PROPOSED PREPAREDNESS, RESPONSE AND REHABILITATION ACTIVITIES (SECTOR BY SECTOR) 4.1. Objective The main objective of the NCP has been addressed in the introduction of this report and is reinforced by sectors based specific objectives i.e. support the timely and coordinated response to anticipated floods in the 2008/09 rainy season, thus effectively minimising the impact of the floods on human population, livelihoods, lifelines and the environment. 4.2. Strategy Mobilize all available resources and deploy them in timely manner to flood affected areas. This will involve implementation of activities in the following areas; 4.2.1. Capacity Building As part of strengthening resilience among communities and strengthening the planning ability, training on preparedness planning in selected flood prone districts will be carried out. This training will focus on risk analysis, assessment and reporting as well as response requirements. 4.2.2. Response In terms of response, concrete sector response plans are developed stating categorically what preparatory actions need to be carried out before, during and after the emergency with built in flexibility to provide for changes in the situation. The response plans also identify gaps where Government will require external support from cooperating partners. 4.2.3. Early Warning/Information Flow The DMMU will work closely with the Department of Water Affairs (DWA) and the Zambia Meteorological Department (ZMD) among others, to ensure that the situation is being monitored as it is unfolding. Regular bulletins preferably on weekly basis generated by DMMU will be circulated as a way of sharing information as the triggers begin to show that the situation is getting worse. The NDMCF which is a coordination mechanism will be called regularly to update the stakeholders on the situation as well as progress on preparedness activities. 4.3. Guiding Principles Humanitarian emergency response will be guided by the principles of neutrality, humanity and impartiality. The response will do no harm and will be based on restoration of affected 8 populations to their former lifestyle without exaggerating and getting populations used to lifestyles they cannot sustain after the emergency. As a guide therefore the government through DMMU will under take to provide as much detailed information as possible regarding the affected populations so that the correct amounts of assistance could be provided. The assistance will also be guided by the fact that this is not development work but short term assistance with possible early recovery programmes. 4.4. Preparedness Activities As part of the implementation most of the work will be concentrated in the preparedness stage i.e. pre-disaster phase. And the Government will consider using the food for work and/or cash transfer programmes to engage communities in these preparedness activities by using initiatives such as food for work to carry out activities such as identification and preparation of alternative sites for relocation. 5.0. RESOURCE GAP ANALYSIS A summary of the resource gap analysis is presented below No Sector Resources Required (ZMK) Resources Available (ZMK) Net Resource Requirement (ZMK) Net Resource Requirement (US$) @ ZMK4500 1 Road Infrastructure 11,000,000,000.00 600,000,000.00 10,400,000,000 2,311,111.11 2 Human Settlement and Shelter 2,245,518,450.00 72,861,633.00 2,172,656,817.00 482,812.63 3 Health and Nutrition 1,090,,608,338.00 50,000,000 1,040,608,332.00 231,246.30 4 Water and Sanitation 15,112,000,000.00 750,000,000 14,362,000,000 3,191,555.56 5 Education 10,612,000,000.00 3,682,000,000.00 6,930,000,000.00 1,540,000.00 6 Agriculture and Food Security 40,466,200,000.00 367,065,644.00 40,099,134,356.00 8,910,918.75 7 Information Management and Emergency Communication 933,483,550.00 269,500,000.00 663,983,550.00 147,551.90 8 Logistics 23,315,884,800.00 - 23,315,884,800.00 5,181,307.73 Total 104,775,695,138.00 5,791,427,277.00 98,984,267,855.00 21,996,503.97 9 6.0. Management and Coordination Arrangements The various coordination forums will continue their coordination activities under the usual overall supervision of the Disaster Management and Mitigation Unit (DMMU), Office of the Vice President. 6.1 The Government through Disaster Management and Mitigation Unit shall coordinate the implementation of the contingency plan. The National Disaster Management Consultative Forum (DMCF) which is co-chaired by the Office of the Vice President and the United Nations Resident Coordinator’s Office shall support DMMU in its coordination role. 6.2 At national technical level the Vulnerability Assessment Committee (VAC) shall support the DMMU in implementing the activities spelt out in the Contingency Plan. 6.3 Within the UN System the United Nations Disaster Management Team under the auspices of the UN Resident Coordinator will implement and coordinate the activities among the UN Agencies before, during and after the disaster. This will be done together with the Inter Agency Standing Committee (IASC) members which includes the International Federation of the Red Cross (IFRC) and both international and national Non Governmental Organisations. 6.4 Other coordination forums such as the International Non Governmental Organisations will continue to meet in coordination meetings with resolutions passed in these forums in response to the emergency communicated to the DMMU in its role as national coordination mechanism. Rapid Assessments and dissemination of related findings should and shall be done within the framework of Zambia Vulnerability Assessment Committee in conjunction with the Provincial, District and Satellite Disaster Management Committees under the overall coordination of DMMU Regional Coordinators. In view of the above undertaking, the Government of the Republic of Zambia will not take kindly to individual organisations that may choose to unilaterally carry out assessments and later on disseminate their findings without Government approval and clearance which should be sought from the Disaster Management and Mitigation Unit. In order to minimise information gaps between different stakeholders, the Permanent Secretary OVP or the National Coordinator of DMMU shall provide updates to line ministry Permanent Secretaries, the Disaster Management Committees and the NDMCF through weekly bulletins. The General public shall be kept updated through press briefings that will be held weekly at a time to be designated. No line ministry at provincial or district level or member of the NDMCF shall unilaterally issue any statement concerning any disaster situation without clearing it first with the respective Disaster Management Committee. The DMMU Regional Coordinators shall ensure that information is timely transmitted and monitor progress of interventions. The Government through Permanent Secretary [A], Office of the Vice President or the National Coordinator at Disaster Management and Mitigation Unit will be holding press briefings every week to update the general public on the floods situation as it evolves around the country as well as the measures being undertaken to address the situation. 10 7.0. Roles and Responsibilities The overall responsibility of coordination shall be with the DMMU in particular and the Office of the Vice- president in general. The Provincial, District and Satellite Disaster Management Committees shall be the local coordination and implementation bodies. There shall be no independent activities carried out by any organisation outside or without the knowledge of the named coordination and implementation bodies. .The National Disaster Management Policy of 2005 places the responsibility of disaster management on the “shoulders” of each one of us, including the Disaster/floods victims themselves. It is in with this in mind that all our cooperating partners such as the UN agencies, donors, and business houses, non-governmental organisations both local and international are called upon to provide assistance during the emergency of contingency plan. 11 Institution Responsibilities Contact DMMU The main responsibility of DMMU will be to receive information, processing it and disseminating it to the stakeholders through the various channels. The other responsibility will be to coordinate the humanitarian response to ensure that there are no duplications for effective humanitarian response. The DMMU will also be responsible for organizing periodic briefings for stakeholders. The DMMU will also be responsible for the mobilization of initial supplies and logistics to enable the cooperating partners come on board in responding to the emergency. Mr. D. Mulenga – +260211253123, +260978881315; Ms. Y. Mwape - +260211252436; +260966754275 Government Ministries The various ministries have the primary responsibility of providing goods and services to the citizens with or without the emergency. The various ministries will therefore be required to continue to coordinate the implementation of sector specific activities related to the humanitarian response and emergency. Ministerial DRR focal points (see Annex….) United Nations Agencies The United Nations has responsibility as the donor of last resort to ensure that they use all mechanisms such as flash appeals, consolidates appeals to mobilize resources for the emergency. It shall be expected that the UN will use their cluster approach as a mechanism around which response to humanitarian response will be organized. The UN on a case by cases basis will activate the clusters to ensure that all resources required are mobilized using their international networks. The UN will be responsible for the coordination of the UN Disaster Management Team and the IASC its members. Mr. Macleod Nyirongo (Resident Coordinator) - +260211254417, +2608772539; Mr. Cheelo Mwiinga (Coordination Officer) +260211251172 ext 271; +260966120021; Mr Pablo Recalde (WFP Country Director/UNDMT Chairperson) +260211252957/250407, +260977790824, Mr James Lynch (UNHCR Representative/UNDMT Deputy Chairperson) +260211265873, +260977862004 12 Institution Responsibilities Contact Non Governmental Organizations (NGOs) These are the primary implementing partners. There major responsibility will be the last mile delivery of humanitarian assistance. They will also be responsible for mobilizing resources in collaboration with the cluster leads under the Inter Agency Standing Committee (IASC) of the United Nations. The NGOs shall be responsible for coordinating the NGO forum and its members. Chair for the INGO forum Private Sector Through their corporate social responsibility and as good corporate citizens, the private sector will be expected to contribute to the humanitarian response in every way possible. It will be expected that as per tradition, the private sector will come to the aid of Government as part of their responsibility to the citizens of this country. Zambia Chamber of Commerce and Industry Chairperson Bilateral Cooperating partners Bilateral cooperating partners have the responsibility of assistance on Government-to-Government basis. The cooperating partners will have the responsibly to work within the existing coordination structures. Bilateral partners are part of the NDMCF and will therefore have the responsibility of attending NDMCF meetings regularly and in turn inform their principle Governments. This will avoid their Governments getting information from the media which in most cases is highly inaccurate. Chair – Donor Humanitarian Group 13 8.0 Resource Mobilisation As per the National Disaster Management Policy of 2005, Disaster Management is the responsibility of everyone. It is line with this that we expect all players ranging from Government Agencies, cooperating partners, the UN System, the Private Sector, Non governmental organisations (Local and International) and those that are community based to be fully involved in the mobilisation of the required resources to implement the contingency plan: 8.1 Cooperating partners are encouraged to indicate to Government through Disaster Management and Mitigation Unit – Office of the Vice President (DMMU OVP) their intention/pledge to donate relief supplies well in advance in order to enable Government follow up on the matter and plan well the utilisation of such resources. 8.2 The pledge in 8.1 above should contain information relating to the target sector, and the value (financial or otherwise) bearing in mind that we are already in an emergency phase of our contingency plan. 9.0. RAPID ASSESSMENTS AND DISSEMINATION OF INFORMATION Rapid assessments and dissemination of related findings should and shall be done within the framework of Zambia Vulnerability Assessment Committee in conjunction with the Provincial, District and Satellite Disaster Management Committees under the overall coordination of DMMU Regional Coordinators. In this regard, the Government of the Republic of Zambia will not take kindly to individual organisations that may choose to unilaterally carry out assessments and later on disseminate their findings without Government clearance. In order to minimise information gaps between different stakeholders during an emergency situation, the Government through Permanent Secretary [A] or the National Coordinator at Disaster Management and Mitigation Unit will be holding press briefings every week on Thursday at 14 hours to update the general public on the floods situation as it evolves around the country as well as the measures being undertaken to address the situation. 14 10.0 Annexes Annex 1: Road Infrastructure Annex 2: Human Settlement and Shelter Annex 3: Health and Nutrition Annex 4: Water and Sanitation Annex 5: Education Annex 6: Agriculture and Food Security Annex 7: Information Management and Emergency Communication Annex 8: Logistics Annex 9: Detailed Sector Resource Gap Analysis Annex 10: Contact Persons 15 Annex 1: Road Infrastructure Sector 1.0. Planning Assumptions It is assumed that Thirty-one (31) Districts from Eight different provinces, namely; North Western, Luapula, Eastern, Southern , Western, Lusaka, Central and Copperbelt Provinces that are likely to receive above-normal Rainfall resulting in flash floods that will cause damage to a large extent on Road embankments and drainage structures such as Bridges, Culverts and other river crossings. With this scenario being very likely, the Agency’s main priority is to provide technical assistance and to ensure that stop-gap measures are put in place to guarantee accessibility and swift return to normality. Agency staff will be deployed to inspect and assess damaged infrastructure in the affected areas. Priority will be given to Feeder roads which are likely to be affected and Crossings leading to essential facilities such as Markets, Clinics and Schools. The following assumptions have been made: � North Western (Mwinilunga, Kabompo, Solwezi, Zambezi and Chavuma) Luapula (Samfya), Eastern (Mambwe, Lundazi and Chama), Southern (Kazungula, Namwala, Itezhi Tezhi, Mazabuka, Monze, Sinazongwe, Siavonga and Gwembe), Western (Senanga, Mongu, Sesheke, Kalabo, Shang’ombo and Lukulu), Central (Kapiri Mposhi, Serenje and Mkushi), Copperbelt (Ndola and Kitwe) and Lusaka (Lusaka, Luangwa and Kafue) provinces are most likely to experience Flooding. � The average cost per Washout is ZMK 270.0 Million (i.e. Complete culvert installation, Headwall and Wing wall Construction, Aprons and Slabs e. t. c.). � Crushing plants for stone aggregates operated by the Road Development Agency will be operational in Southern, Copperbelt, Eastern, western, North Western, Central, Luapula, Northern and Lusaka provinces. � Other institutions such as Zambia Army, ZNS and Buildings Department (Ministry of Works Supply) have capacity to provide temporary bridges and heavy equipment to facilitate emergency works. � Contractors in the vicinity of disaster areas will be compelled to help in the event of a disaster and be paid for the service. � Routine maintenance will limit the number of Washouts of roads and bridges. � Resources for repair of damaged infrastructure will be provided promptly and will be given first priority. � Pipe Culverts and Portal frames from the known suppliers will be readily available. 2.0. Overall Objectives The overall objective is to provide accessible Road and Bridge infrastructure to ease mobility of people as well as movement of relief Supplies to populations that will be displaced by floods. 3.0. Specific Objectives Specific objectives include: � Identify and formulate intervention strategies needed for road infrastructure before, during and after the floods. � Provide reliable road Access, Bridges and Culverts in flood prone areas thereby increasing mobility of relief supplies to affected populations immediately, during and after the floods. � Provide and disseminate information on alternative routes and available pontoon 16 services in and around distressed areas. 4.0. Requirements � Utility vehicles with Four-Wheel-Drive capability. � Communication equipment (Two-way Radios) / laptops with wireless connection, Cameras. � Heavy construction Equipment to be provided by third parties including newly Road equipment from China per province will include; 1No.Wheel loader/ Excavator, 1No.Dozer, 2No.Graders, 1No.Roller, 3No.Tippers, 1No.Low bed, 1No.Truck with lifting arm or Crane and, 1No.Water Bowser. � Other necessary materials such as culverts (Box and pipe) Logistics to be used on the works � The Concrete Pipe and Box culverts will be obtained from Lusaka and Ndola. � The stones will be obtained from Lusaka, Southern, Central, Northern, Copperbelt and Eastern Provinces. � Coarse and fine aggregates can be sourced from within the respective districts. a. Portland cement will be supplied from Lusaka and Ndola. b. Manual labour will be sourced from the affected areas. c. Bailey Bridges will be sourced within the country, where available. 5.0. Implementing Agencies � Road Development Agency � Zambia National Services � Zambia Army � Roads Unit under Buildings Department 17 6.0. Activities 6.1.. Activities To Be Undertaken Before An Emergency No. Activities Facilitator Supported by By when 1 Sensitization of all Regional offices RDA – HQ DMMU Immediate 2 Development of an early warning system for potential failures of culverts and Bridges through a Bridge management system RDA - HQ/Regional DMMU Immediate 3 Preventive/routine maintenance on rural, feeder and district roads RDA - HQ/Regional DMMU Immediate/on-going 4 Clearing and desilting of waterways and drainages structures RDA - HQ/Regional DMMU Immediate/on-going 5 Replacement and maintenance of Guardrails on flood prone crossings RDA - HQ/Regional DMMU Immediate 6 Assessment and monitoring of conditions of bridges and road service levels through Bridge and road conditional surveys. RDA - HQ/Regional DMMU Immediate/On-going 6.2.. Activities to be undertaken During an emergency # Activities Facilitator Supported by By when 1 Monitor performance of prone crossings and effect of water levels RDA – HQ DMMU Immediate/On going 2 Provide expertise to assess damage RDA - HQ/Regional DMMU Immediate/On going 3 Provide Guidance on how to remedy damage RDA - HQ/Regional DMMU Immediate/On going 4 Provide temporary crossings and access routes RDA - HQ/Regional DMMU/Zambia Army/ZNS Immediate/On going 5 Provide information through warning signs RDA - HQ/Regional DMMU Immediate/On going 6 Provide information on alternative routes RDA - HQ/Regional DMMU Immediate/On going 7 Monitor effectiveness and provide information on available Pontoon services RDA HQ/Regional/ESCO DMMU Immediate/On going 18 6.3.. Activities to be undertaken after an emergency No. Activities Facilitator Supported by By when 1 In-depth assessment of flood impact on road infrastructure and crossings RDA - HQ/Regional DMMU March, 2009 2 Review of performance of various structures after Floods RDA - HQ/Regional DMMU April, 2009 3 Identification of remedial needs and intervention methods for damaged infrastructure RDA - HQ/Regional DMMU April, 2009 4 Prioritization of damaged road infrastructure/bridges RDA - HQ/Regional DMMU June, 2009 5 Generate Cost estimates and mobilize resources RDA - HQ/DMMU DMMU July, 2009 6 Planning and implementation of recovery Phase RDA - HQ/DMMU DMMU July, 2009 7 Monitoring and Evaluation of recovery phase RDA - HQ/DMMU DMMU Sept, 2009 7.0. Summary of the Budget No. Item Cost (K) 1 Emergency infrastructure technical assessment 450,000,000.00 2 Review of performance of various structures after floods 200,000,000.00 3 Identification of remedial needs and intervention methods for damaged infrastructure 150,000,000.00 4 Prioritization of damaged road infrastructure/ bridges 100,000,000.00 5 Generate cost estimates and mobilize resources 100,000,000.00 6 Bridges/ roads emergency repairs 10,000,000,000.00 TOTAL 11,000,000,000.00 19 7.1. Detailed Costings for Road Infrastructure CENTRAL PROVINCE IN-DEPTH ASSESSMENT OF 2007/08 FLOOD IMPACT Priority Order District Road Name Road Code Chainage of Defect Point* Nearest Main Road Code Ward/Village Settlement Type of Structure Name of River/Stream Crossing Extent of Damage Proposed Intervention Estimated Cost (ZMK) 1 Kapiri Mposhi Mukobeko-Ngabwe D817 various T2 Bwacha, Kapiri Mposhi Ring Culvert Several streams Deep erosion gullies & armco culverts vadalised and collapsed Spot improvement at various chainages, Instal 12No.lines X 900mm Culverts 150,000,000 2 Kapiri Mposhi T2-Muteteshi Unclassified 30 T2 Ring Culvert Muteteshi stream Culvert washed away and eroded embankment Construct a vented drift and repair the culvert headwalls and wingwalls 150,000,000 3 Mkushi Masansa-Mboroma RD208 90 Chabanga Ring Culvert Chabanga Stream Culvert washed away Instal 2No. x 1800 x 1800 Portal Frame and 2No. x 900 Relief culverts 4 Mkushi Mkushi-Upper Lunsemfwa Unclassified 10 T2 Milombe Ring Culvert Milombe stream Culvert washed away Construct a vented drift and instal 2No. x 900mm culverts 100,000,000 5 Mkushi Masansa-Mboroma RD208 176 T2 Mkushi North Ring Culverts Misansa Culverts washed away. Install 2 x 1500 x 1500 portal frames 100,000,000 6 Serenje Kundalila-Katota School Unclassified 79.7 D224 Kundalila Ring Culverts Miswema river Culverts washed away. Install 3 x 900mm culverts 150,000,000 7 Kapiri Mposhi Mang'ola - Lunchu Unclassified 26.5 T2 Ring Culverts Lunchu Stream Culverts washed away. Instal 3No. 1500 x 1500 Portal Frames, and raise embankment Total Cost of Reinstatements 650,000,000 20 COPPERBELT PROVINCE CONTIGENCY PLAN Item no District Road Name Road Code Chainage of Defect Point Nearest Main Road Code Ward/Village Settlement Type of Structure Name of River/Stream Crossing Construction Details Date of Damage Extent of Damage Proposed Intervention Estimated Cost (ZMK) 1 Ndola 2 + 500 T3 Kavu Ward Make shift bridge (timber) Munkulungwe Nil Dec-06 (a) Washed away makeshift bridge (b)Damaged approaches to bridge (20m stretch) a) Installation of 900mm culvert pipes x 4No. b)Repair damaged approaches H = 1.5m,W=5.5m , L = 20m 80,000,000 2 Ndola Kavu road earth 3 + 000 T3 Kavu Farm Block Embankment Munkulungwe Feb-07 Approaches to bridge eroded regravelling of approaches to bridge 42,000,000 3 Ndola Madando Feeder 0 + 500 T3 Twapya Culvert Twapya Culvert Type:Armco,Pipe Diameter:900mm,He ad wall type:Stone masonery,Total Length: 6.8m, Embankment Height:1.5m Jan-07 (a) Damaged stone masonery wingwall (b)Eroded embarkment (2m x 1m X 7.5m) (a) Replace damaged wingwall (b) Backfill and compact embarkment 35,000,000 4 Kitwe Presidential Guest House rd earth 0 + 850 T3 Kamfinsa Culvert Matemate Culvert Type: Concrete box, No. of Lines: Two (2) Cells, Pipe Diameter: 3.5m per channel, Head wall type: Concrete Total Length:7.0m, Embankment Height: 5m Nov-07 (a) Washed away wingwall, (b) Cracked wingwall & abutment joint, (c) Eroded embarkment behind wingwall 6m X 2m deep, (d) Eroded embarkment (2.5m x 5m X 8.0m) (a)Provide for new wing wall to culvert, (b) Seal crack in joint between wingwall and Abutment, (c)Backfill and compact erosion craters and provide embarkment protection by stone pitching 60,000,000 Total Cost of Reinstatements 217,000,000 21 EASTERN PROVINCE CONTIGENCY PLAN Item No District Road Name Distant from the Center. Chainage of Defect Point Nearest Main Road Code Ward/Constituency Type of Structure Name of River/Stream Crossing Type of Damage Proposed Intervention Estimated Cost (ZMK) 1 Chama Chama - Kambombo 1km Kamphemba Ward, Chama North Drift Kamphemba The river changed course and eroded the grift are side Extension of the drift/construction of a bridge on another point 60,000,000.00 2 Chama Chama - Kambombo 4km Kamphemba Ward, Chama North Box culvert Kazoo Crack on the deck eroded apron and broken wing walls Replacement of deck apron and wing walls 40,000,000.00 3 Chama Chama - Kambombo 7km Mphalausenga Ward. Chama North Box culverts Vitukutu Cracks on the deck Replacement of the deck 25,000,000 4 Chama Chama - Kambombo 10km Mphalausenga Ward in Chama North Culverts Pendwe Culverts silted discharge drains low embankment s Opening drainage and culverts raising embarkment 50,000,000 5 Chama Chama - Kambombo 15km Mphalausenga Ward. Chama North Culverts Mbwata Water crossing the road 5m before the culverts Construction of a Catch Water drain. 15,000,000 6 Chama Kalinkhu - Nthonkho 23km Kalinkhu - Chama North Box culvert Chaubwa Completely washed away box culverts Construction of a new drift 100,000,000 7 Chama Hospital Road Within the Township Kamphemba Box culvert Kanjiki No wing walls Construction of wing walls 50,000,000.00 8 Chama Chama - Tembwe 24km Mabinga Drift Bazimu Eroded hand wall and damaged back Rehabilitation of head wall 50,000,000.00 9 Chama Tembwe - Chikwa 42km Mabinga Box culvert Chizizi Washed away wooden deck Replacement of wooden deck with concrete deck 40,000,000.00 22 EASTERN PROVINCE CONTIGENCY PLAN Item No District Road Name Distant from the Center. Chainage of Defect Point Nearest Main Road Code Ward/Constituency Type of Structure Name of River/Stream Crossing Type of Damage Proposed Intervention Estimated Cost (ZMK) 10 Chama Tembwe - Chikwa 64km Lumezi Box culvert Lumezi Washed away wooden deck Replacement of wooden deck with concrete deck 40,000,000.00 11 Lundanzi Champhoyo Mwasemphangwe Scheme 80km Lumezi Plank Foot bridge Mwase Bridge washed away Construction of concrete culvert 100,000,000.00 12 Ludanzi Kawinga - Yokobe 70km Lumezi Drift Chikomeni Bridge damaged, washed away Construction of Drift 100,000,000.00 13 Ludanzi Zumwanda - Bulete 35km Lumezi Culverts Mthilakubili Damaged culvert Construction of 2 x 900mm dia culverts 90,000,000.00 14 Ludanzi Zozo 50km Chasefu Plank Foot bridge Zozo Bridge washed away Contruction of cone Box culverts 100,000,000.00 15 Ludanzi Chasefu - Egichikeni 80km Chasefu Conc Deck Bridge Chasefu Contructe Deck collapsed Contruction of concrete box culverts 100,000,000.00 16 Ludanzi Hoya - Kamuzoole 70km Chasefu Drift Hoya Drift damaged Construction of Drift 60,000,000.00 17 Ludanzi Z.. N. S - Mwase Turnoff 65km Lundazi Drift Pharaza Drift damaged and washed away Construction of Drift 120,000,000.00 18 Ludanzi Mwase - Ndonda 50km Lundazi Culverts Ndonda Damaged culvert Contruction of concrete box culverts 120,000,000.00 19 Maambwe Sanjemuleke 2km Lundazi Culverts Kalopa Damaged culvert and washed away Contruction of concrete box culverts 20 Maambwe Chilipadambo 3km Lundazi Drift Lundazi Damaged drift Construction of Drift 21 Maambwe Mphamba - Msuzi 10km Lundazi Culvert Msuzi Damaged culverts Contruction of culverts Total Cost of Reinstatements 1,260,000,000.00 23 LUAPULA PROVINCE CONTIGENCY PLAN Item No District Road Name Road Code Chainage of Defect Point Ward/Village Settlement Type of Structure Name of River/Stream Crossing Construction Details Proposed Start Date Date of Damage Extent of Damage Proposed Intervention Estimated Cost (ZMK) 1 Samfya Culverts Ing'anda Imo Stream 3 lines by 900mm concrete culverts. 130,000,000.00 2 Samfya Varous Culverts Mwalashi Stream 5 Lines of 1200mm concrete pipe culverts 3 Samfya Varous Culverts Lupenda Stream 2 Lines of 900mm Concrete Pipe 100,000,000.00 4 Samfya Varous Culverts 3 lines by 900mm concrete culverts. 130,000,000.00 5 Samfya Varous Culverts 2 Lines of 900mm Concrete Pipe 100,000,000.00 6 Samfya Nsonga Tande Mulumbi Road Culverts 8 Lines of 900mm Concrete Pipe 7 Samfya chsunka Chofwe Chipili Road Culverts 2 Lines of 1200 mm (Duoble) Concrete Pipe and 3 Lines of 900 mm at Bembe Dambo 130,000,000.00 8 Samfya Kamami Mutipula Road Culverts 2 Lines of 900mm Concrete Pipe 100,000,000.00 9 Samfya Culverts Moonga stream 2Lines of 900mm Concrete Pipe 100,000,000.00 Total Cost of Reinstatements 790,000,000.00 24 LUSAKA PROVINCE CONTIGENCY PLAN Item No District Road Name Road Code Chainage of Defect Point Nearest Main Road Code Ward/Village Settlement Type of Structure Name of River/Stream Crossing Construction Details Proposed Start Date Date of Damage Extent of Damage Proposed Intervention Estimated Cost (ZMK) 6 Luangwa Mpashya U21 T4 Mpashya Clinic No structure Narow and Dilapidated Timber structure 2004 2008 Narrow and dilapidated timber structure Install 2 x 1200mm dia including headwalls and wingwalls 100,000,000.00 7 Luangwa Luangwa Road D145 37+600,1+900, 10+800,17+30 0 Ring Culverts Prone to flash floods. Requires installation of 600mm and 900mm culverts Jun-08 2008 Existing structure and points becomes flooded in the rain season most culverts have been damaged and need replacement. Installation of 1x600mm culvert and 1x900mm culvert on various points 65,000,000.00 8 Lusaka Great East Road T4 71+400 T4 Armco Culverts Mambwe stream Damaged apron causing ingress of water in the all structure Jun-08 2008 Apron has been damaged,end wall stone pitching has collapsed need for stone pitching and bachfilling with stabilized gravel. Backfilling and stabilization of damage inlet to the culvert 9 Lusaka T4-Shikabeta Road RD146 T4 Just before Shikabeta Clinic 900mm Dia. existing Requires additional culverts 2006 Erosion of embankment because existing culvert is inadequate Install 2 x 900mm dia additional culverts including construction of headwalls and wingwalls 100,000,000.00 10 Lusaka Kridge D178 T2N Kridge farm Splash Damaged splash 2006 Damaged splash Install 3 x 900mm dia culverts 120,000,000.00 11 Lusaka Leopards/Mika ngo 18+000 D152 Drift Culverts Njolwe Stream Collapsed Culvert Jun-08 2004 Failure of concrete deck due to collapsed culverts. Demolish existing structure and construct a new one.New reinforced structure and stone pitch. 12 Lusaka Chiawa and Mugurameno U10 and Rd117 13+300 and 13+600,21+10 0,30+900,31+6 00,41+500 D481 Culverts Ring Culverts June 2006 Replace damaged culverts with 600mm culverts,9No.x 900mm culverts,1No.x 900mm culverts and 2No. Lines x 900mm culverts 2008 Remove Existing and damaged/Washed away pipes and culverts 120,000,000.00 25 LUSAKA PROVINCE CONTIGENCY PLAN Item No District Road Name Road Code Chainage of Defect Point Nearest Main Road Code Ward/Village Settlement Type of Structure Name of River/Stream Crossing Construction Details Proposed Start Date Date of Damage Extent of Damage Proposed Intervention Estimated Cost (ZMK) 13 Lusaka Situmbeko and Chimbotela D535 M009 Culverts Eroded culverts pipes Jun-08 2008 Replace damaged culverts with 3 No. lines and raise road by 500mm over a 25m section Replace damaged culverts with 3 No. lines and raise road by 500mm over a 25m section 150,000,000.00 14 Kafue Kafue 19+100,19+ 400,19+ 600,59+ 100,60+ 100 T2 S Culverts Repair the steel guardrails, backfilling and stone pitching of the erosional damage. May-08 2008 Damaged guardrails,cutting of road shoulders and undercutting of the road side. Repair damaged guardrails with remaining components, provide gabion baskets on eroded sections 100,000,000.00 15 Kafue Kafue T2S T2S Culvert Extend one culvertring and fill & stone pitch with rubble Apr-08 2008 Erosional damage on the outlet side of the culvert. Extend culvert ring and stone pitch 100,000,000.00 Total Cost of Reinstatements 855,000,000.00 26 NORTH-WESTERN PROVINCE CONTIGENCY PLAN Item No District Road Name Road Code Chainage of Defect Point Nearest Main Road Code Type of Structure Name of River/Stream Crossing Construction Details Proposed Start Date Date of Damage Extent of Damage Proposed Intervention Estimated Cost (ZMK) 1 Mwinilunga 3+500 Kampemba Decayed timer deck Submerged timber slippers. Replace the deck. 2 Mwinilunga 25+000 Kankanja Erosion Gullies. Install 4 x 900mm. Dia Culverts 3 Mwinilunga Mwinilunga to Jimbe T005 30+000 Mwinilunga to Jimbe Erosion Gullies. Install 4 x 900mm. Dia. 100,000,000.00 4 Mwinilunga 40+000 Nyamakabila Erosion Gullies. Install 4 x 900mm. Dia. 100,000,000.00 5 Mwinilunga Lwekela to Kakoma RD 276 115+000 Kalukundu bridge Timber members burnt by fire. Replace bridge with RC. 250,000,000.00 6 Mwinilunga Nsweta to Kakoma Mujila Bridge Damaged timber deck. Construct new RC Bridge 7 Mwinilunga Kanongesha to Kamapanda RD 289 60+000 Kasenga Deck swept by rains rosion gullies on approaches Construct new RC Bridge 8 Mwinilunga Ntambo to Kasanjiko Kasanjiko Culverts. Embankment eroded, Collapsed Culverts. Reconstruct embankment and nstall 4 x 900mm. Dia. 9 Zambezi Dipalata to Kakeki RD 294 Eroded approaches and Embankment. Reconstruct embankment approaches and repair 30,000,000.00 10 Zambezi Mize to Chinyama Litapi RD 296 70+000 Mukema Timber bridge with beams and logs laid across the Road Construct new RC install 2 x 900mm Dia 100,000,000.00 26 Solwezi Lamba R184 10+000 Lamba Washed away timer logs. Replace with Construct 2 x 900mm dia Culverts 90,000,000.00 27 Solwezi Kisalala to Lunga U26** Lunga bridge Washed away timber slippers and embankment approach. Replace with Construct 2 x 900mm dia Culverts construct embarkmen. 27 NORTH-WESTERN PROVINCE CONTIGENCY PLAN Item No District Road Name Road Code Chainage of Defect Point Nearest Main Road Code Type of Structure Name of River/Stream Crossing Construction Details Proposed Start Date Date of Damage Extent of Damage Proposed Intervention Estimated Cost (ZMK) 28 Solwezi 8+00 Solwezi Crossing(Kimas ala) Slippers and embankment washed away. Replace with Construct 2 x 900mm dia Culverts construct embarkmen. 29 Solwezi Kalulushi to Kesempa M018 100+000 Musakashi Erosion on the western side. Repair / Replace 1x900mm dia 30 Solwezi Matebo Maheba Mafwe Damaged timber deck Replace with Construct 2 x 900mm dia Culverts 31 Kabompo U9 102+000 Ndunga culverts.(Ndung a - Luansonga Embarment) Submerged and approach is washed away Install 2 x 900mm. Dia Culvert. 100,000,000.00 33 Chavuma Chavuma to Litapi U11 40+000 Umbuze Timber bridge with beams and slippers washed away. Construct new RC bridge. 150,000,000.00 34 Chavuma Chavuma to Litapi U11 62+000 Kakonge Timber bridge with beams and slippers washed away. Construct new timber bridge. 60,000,000.00 35 Chavuma Chavuma to Litapi U11 62+000 Chiseso Washed away culverts Replace with Construct 2 x 900mm dia Culverts 90,000,000.00 36 Chavuma Chavuma to Litapi U11 102+000 Kapopolu Washed away culverts Replace with Construct 2 x 900mm dia Culverts 90,000,000.00 37 Chavuma Kalombo to Chikongolo 25+000 Kalombo Timber bridge with beams and slippers washed away. Construct 3 x 900mm dia Culverts 38 Chavuma Chavuma to Mize RD 552 08+000 Mavili Damaged wingwalls. Repair Total Cost of Reinstatements 1,160,000,000.00 28 SOUTHERN PROVINCE CONTIGENCY PLAN Item No. District Road Name Road Code Chainage of Defect Point Nearest Main Road Code Ward/Village Settlement Type of Structure Name of River/Stream Crossing Type of Damage Proposed Intervention Estimated Cost (ZMK) 1 Gwembe Bottom D500 MASIKILI Drift Washed Away Reconstruction 2 Gwembe Bottom D500 Ch4+700 Drift Rehabilitation 3 Gwembe Bottom D500 Ch6+800 Solid Drift Reconstruction 100,000,000.00 4 Gwembe Bottom D500 Ch8+000 Drift Rehabilitation 100,000,000.00 5 Gwembe Bottom D500 Ch 9+500 Drift Rehabilitation 100,000,000.00 6 Gwembe Bottom D500 Ch60+000 Drift Koma river Washed awayed Reconstruction 100,000,000.00 7 Gwembe Bottom U9 Ch19+920 Embankment &Culvert washed away Reconstruction 100,000,000.00 8 Namwala Naminwe Bridges M11 Erosion Gullies Concret works. Filling eroded bidge foundation and protection against erosion 9 Namwala M11 Damaged culverts Repair/reconstruction of culverts 10 Kazungula Makunka Nyawa M10 Ch32+000 Makunka Drift Washed away drift Reconstruction 150,000,000.00 11 Mazabuka Chaanga Malabo D387 Ch43+400 Chikankanta Drift Jalala vented drift washed away. Width at cross point of stream channel 45m Construction of a neww drainage structure 150,000,000.00 12 Mazabuka Chingangauka Chikani Ch1+200 T1 Culvert Original culvert washed away. Gulley at this point 2.5m deep and 18m Length. Construction of a box culvert 150,000,000.00 13 Itezhi-tezhi Nakabangwe Rd box culvert Crossing damaged Repair of embankment/repair of crossing 200,000,000.00 14 Itezhi-tezhi Baanga box culvert Crossing damaged Repair of embankment/repair of crossing 200,000,000.00 15 Itezhi-tezhi Bachele box culvert Crossing damaged Repair of embankment/repair of crossing 150,000,000.00 16 Itezhi-tezhi Chile Village box culvert Crossing damaged Repair of embankment/repair of crossing 150,000,000.00 29 SOUTHERN PROVINCE CONTIGENCY PLAN Item No. District Road Name Road Code Chainage of Defect Point Nearest Main Road Code Ward/Village Settlement Type of Structure Name of River/Stream Crossing Type of Damage Proposed Intervention Estimated Cost (ZMK) 17 Siavonga At Nabbanda Box culvert Damaged crossing/eroded approaches Repair of embankment/repair of crossing 18 Siavonga At Shamwiinga box culvert Damaged crossing/eroded approaches Repair of embankment/repair of crossing 19 Siavonga At Diddwi Culvert Damaged crossing/eroded approaches Repair of embankment/repair of crossing 200,000,000.00 20 Siavonga At Jamba Culvert Damaged crossing/eroded approaches Repair of embankment/repair of crossing 80,000,000.00 21 Sinazongwe At Donga Stream Culvert Damaged crossing/eroded approaches Repair of embankment/repair of crossing 22 Sinazongwe Kalinkoto Stream Bridge Damaged crossing/eroded approaches Repair of the bridge 150,000,000.00 23 Sinazongwe kama kwiyu stream Bridge Damaged crossing/eroded approaches Repair of the bridge 100,000,000.00 24 Sinazongwe Kamalavu Bridge Damaged crossing/eroded approaches Repair of the bridge 25 Sinazongwe Kamangedeni Bridge Damaged crossing/eroded approaches Repair of the bridge 26 Siavonga At Sinachilombo Culvert Damaged crossing/eroded approaches Repair of embankment/repair of crossing 88,000,000.00 Total Cost of Reinstatements 2,268,000,000.00 30 WESTERN PROVINCE CONTINGENCY PLAN Iterm no District Road Name Road Code Chainage of Defect Point* Nearest Main Road Code Ward/Village Settlement Type of Structure Name of River/Stre am Crossing Construction Details Proposed Start Date Date of Damage Extent of Damage Proposed Intervention Estimated Cost (ZMK) 1 Senanga Kalabo-sitoti D319 60km Senanga central Road embankment and armco culverts at 3 points of the road At first point 60m of embarkment has been washed away exposing 2 culverts at either ends. At second point culverts are inadequate therefore the fill material on culverts and some culverts have been washed away. At third point 40m of embankment has been washed away exposing the armco culverts below. There are 9×900mm diameter at the bottom and 9×600mm diameter culverts on top.All headwalls and wing walls have collapsed.These drainage structures are inadequate. 22/02/08 The road is impassable,acc ess to the washaway at the moment is by water from senanga. Replace the damaged armco pipes with concrete pipes and reconstruct the embankment as follows: At point one install 4 sets consisting 3No. ×1800mm culverts spaced at 10m. At second pointinstall 3No. × 1800mm diameter culverts. .At third point install 8No.× 900mm diameter culverts 350,000,000 2 Senanga Kafula Namabunga Bridge has been damaged Lui River Bridge Rehabilitation Bridge Rehabilitation 250,000,000 3 Kalabo Lundilwe Bridge has been damaged Lundilwe River Bridge Rehabilitation Bridge Rehabilitation 250,000,000 4 Kalabo Silamu Bridge has been damaged Silamu Stream Bridge Rehabilitation Bridge Rehabilitation 250,000,000 5 kalabo Lilengo bridge Bridge has been damaged Lilengo River Bridge Rehabilitation Bridge Rehabilitation 250,000,000 6 kalabo Kataba school bridge kalabo Bridge has been damaged Bridge Rehabilitation Bridge Rehabilitation 250,000,000 31 WESTERN PROVINCE CONTINGENCY PLAN Iterm no District Road Name Road Code Chainage of Defect Point* Nearest Main Road Code Ward/Village Settlement Type of Structure Name of River/Stre am Crossing Construction Details Proposed Start Date Date of Damage Extent of Damage Proposed Intervention Estimated Cost (ZMK) 7 kalabo Mwandi Culvert kalabo Replacement of washed away culvert 4No. × 900mm diameter culvert(first crossing point).The embankment length is 1.850km and 4.5m wide. The road is impassable Replace the armco pipes with 3No. × 900 mm concrete culverts 150,000,000 8 kalabo Kachumwa kalabo Bridge has been damaged The Bridge span is 10m and 1.2m high Rehabilitation of the damaged bridge. 9 kalabo Kalabo sikongo RD 315 33.5km and 38km respectively Sikongo Road embankment and armco culverts at 3 points of the road 600mm dia. Armco Culverts and at two other points about 50m of embankment around Ch 33+500 from kalabo have been washed away where as at Ch 38+000 about 40m long of the embankment has been washed away 27/02/08 The washaway at chainage 38+000 is very severe traffic can hardly cross Replace the damaged armco pipes with concrete pipes and reconstruct the embankment.A total length of 150m of the embankment needs to be reconstructed and raised to 1.2 and 1.9 around chainage 33+000 and 38+000 respectively. 300,000,000.00 10 Mongu Namushakende Nalikwanda RD 305a 60Km Nalikwanda Armco Culverts at chainage 39+500 from M10 junction 3 No. × 600mm diameter 20/01/08 The culvert lines have collapsed leaving adeep depression on the road. Replace the armco pipes with 3No. × 900 mm concrete culverts 100,000,000.00 11 Mongu Nalikwanda Litawa road U17 75Km Nalikwanda Embankment with Culvert crossing points 4No. × 900mm diameter culvert(first crossing point).The embankment length is 1.850km and 4.5m wide. 20/01/08 The embankment has severely eroded and water is overtoping in most sections.Two lines of culverts at first point have collapsed. Replace the collapsed armco pipes with 2No. × 900 mm concrete culverts . Construct new concrete culverts 2No.×900mm diameter at 3 points on ch 0+600 ,Ch 1+300 and ch 1+620. Repair and raise embankment by 0.5m. 32 WESTERN PROVINCE CONTINGENCY PLAN Iterm no District Road Name Road Code Chainage of Defect Point* Nearest Main Road Code Ward/Village Settlement Type of Structure Name of River/Stre am Crossing Construction Details Proposed Start Date Date of Damage Extent of Damage Proposed Intervention Estimated Cost (ZMK) 12 Mongu Lueti Clinic Stream Culvert washed away Lueti Clinic Stream 3 No. × 600mm diameter 150,000,000 13 Mongu Liande Namengo Road. U14 105 Nalikwanda Embankment with Culvert crossing points At chainage 0+870 embankment length of 15m long and 1.5m high has been washed away.The log bridge at chainage 1+140 has a span of 12m on the main river. 20/01/08 At ch 0+965 on embankment the culvert outlet head wall,wingwalls have been washed away and the whole structure is likely to be washed away in the next heavy rainfall.At chainage 1+140 on the embankment,a log bridge has deteriorated and water is almost overtoping the bridge. Construct 1No.×1500mm culvert(ch 0+870),replace armco culvert(ch 0+965) concrete pipes 2x900mm concrete and construct 2No.× 1200mm culverts(ch 1+140) 150,000,000 14 Mongu RD312 RD3 12 145 Simaa ward/ Luena constituency Three timber bridges at Nangandu river have been washed away.At Naluwe flood plain there is need to construct an embankment 0.2km of embankment across Nangandu river.3No. Timber bridges have been washed away at 3 different points of the embankment.The first point is 2m deep and the other two points are 1.5m deep.At Naluwe construct an embankment of 333m by 1m high. 03/10/2008 The embankment is very low.Access to the wash aways requires use of 4×4 vehicles. At the wash away construct 2No.×2400mm Box Culvert and 4No.×1500mm Box Culvert culverts and at Naluwe construct an embankment 200,000,000 33 WESTERN PROVINCE CONTINGENCY PLAN Iterm no District Road Name Road Code Chainage of Defect Point* Nearest Main Road Code Ward/Village Settlement Type of Structure Name of River/Stre am Crossing Construction Details Proposed Start Date Date of Damage Extent of Damage Proposed Intervention Estimated Cost (ZMK) 15 Senanga old M10 Old M10 30 km Nanjucha Bridge has been washed away at chainage 14+500 and at chainage 14+800 culverts are blocked The Bridge span is 15m and 1.2m high 01/12/2008 The bridge was washed away sometime in 2007 and the community have since built a temporary crossing structure Construct 4No. By 1500mm diameter culverts and unblock the culverts at ch 14+800 and add more fill. 150,000,000.00 16 shangom bo Rd 463 Rd 463 110Km from Matebele. Sinjembela Embankment washout About 15m long and 1.5m high embankment washout March,2008 Road is impassable Repair embankment and construct culverts Total Cost of Reinstatements 2,800,000,000 34 Annex 2: Human Settlement and Shelter Sector 1.0 Planning Assumptions In the most likely scenario where it is expected that 15,972 or 2,662 households will be affected by the floods in 9 districts. Of these about 11,981 persons or 1996 households will need temporal shelter and non food items for more than 2 weeks. In addition some families may require sleeping mats, blankets, mosquito nets, water containers, cooking utensils and charcoal, etc. Also it will be necessary to implement appropriate camp management procedures to ensure effective prevention and control of diseases as well as adequate protection of the most vulnerable among the displaced population. Where the affected population will need temporal shelter for more than 2 weeks, districts authorities will allocate appropriate sites for the installation of temporal camps. In this situation, in addition to the distribution of Non food items to the displaced families and to camp management activities, it will be necessary to do site identification and site planning before the end of January 2008. Shelter in the camps will be rub-halls, plastic sheeting, poles and to the extent possible tents. DDMCs and concerned organizations will identify the most suitable form of shelter in potential sites. 2.0. Overall Objective The overall goal is to provide temporal shelter where necessary to the displaced persons in order to minimise human suffering as a result of the disruption of their economic activities and destruction of their houses by the floods. 3.0. Specific objectives The specific assumptions are as follows: 1. To provide shelter to the displaced persons 2. To provide basic households items to the most vulnerable households among the displaced population 3. To ensure that all camp sites are located in areas accessible by all-weather roads 4. To ensure that family unity is maintained when allocating shelter to affected households 5. To ensure easy access to relief supplies by displaced persons in various camps 6. To ensure protection and security of the most vulnerable persons among the displaced in the camps and or settlements a. Scenario Building Projection Table Variable Expected Events/Effects over the Next Six Months Time Frame Assumptions if any People Displaced Damaged houses and other infrastructure due to excess rainfall and flooding November to April i. Raised down houses and other infrastructure ii. Damaged roads & bridges iii. Erratic supply of social amenities 35 b. Scenario Building Projection Table Effects Effects on Households Direct Effect Indirect Effect Damaged houses and other Infrastructu re i. Loss of house accommodation ii. Loss of livelihood iii. Degraded environment iv. Possibility of disease outbreaks due to poor sanitation v. Lack of access to social amenities vi. Migration of people to safe areas i. No shelter ii. No food iii. No sanitary system iv. Contaminate d water v. Risk of death due to drowning vi. No access to social amenities i. People exposed to cold weather and rain ii. People will starve iii. People will be susceptible to disease iv. Trauma associated with death of a family member v. No access to social amenities The following districts and number of people are likely to be affected. This will require government intervention in terms of relocating the affected households to higher and safer lands and provision of food supplies and other services. District Projected No. Household to be Affected No. of Tents Required Tents Required at 10% Contingency Gwembe 150 150 165 Itezhi-tezhi 200 200 220 Lukulu 200 200 220 Mazabuka 200 200 220 Monze 250 250 275 Mumbwa 500 500 550 Namwala 500 500 550 Sinazongwe 150 150 165 Solwezi 270 270 297 Total 2420 2420 2662 4.0. Requirements Shelter in form of tents will be provided to each displaced household and as much as possible, family unity will be maintained by providing adequate number of tents per family. This will ensure children’s safety and reduced cases of child abuse. 4.1. Site Identification and Planning Temporal Site Under this arrangement, the projected number of households that would be displaced temporarily is 3,996 persons or 666 households and will require sufficient number of tents to cater for the affected population. Site identification and planning for temporal relocation of affected households will be done by the DDMCs and concerned organizations will identify the most suitable form of shelter in potential sites. Permanent Sites-Urban For permanent sites in urban areas, the local authorities i.e. the district councils will be engaged to plan and provide alternative land for resettling of the displaced households. Permanent sites-rural: for rural sites, the Department of Resettlement in collaboration with the District Administration will be engaged to identify and plan such sites. Site planning will involve developing of site plans, demarcation of plots and subsequent allocation of such plots. The minimum size of plots being 4 Ha while the maximum is 50ha per household. For rural 36 permanent sites, the minimum land mass that would be required to permanently relocate the displaced households settled in flood prone areas is approximately 8,000 hectares. 4.2 . Water Water collection points will be in a maximum distance of 500 m from each shelter and will provide at least 15 litres of water per person per day. When necessary each household will be provided with at least two 20 litres containers with lids. It may also be necessary to provide each family with a 30 litres bucket. 4.3. Sanitation An average of one latrine seat will be available for 20 persons. The distance between the shelters, the water collection points and the latrines will be at least 50 m. Adequate hygiene promotion and vector control activities will be done on regular basis with the full participation of the displaced population. 4.4. Other Non-Food Items When necessary, adequate quantities of soap, sleeping mats, blankets, mosquito nets, used clothes, cooking utensils and fuel to meet cooking and heating needs will be provided to affected households. Also necessary sanitary napkins for women and girls in child-bearing age will be distributed. In addition adequate quantities of condoms will be available for targeted distribution. As much as possible the Sphere standard on Non Food Items will be respected namely: � Per person: 1 sleeping mat, 1 blanket, 1 cooking set. � Per family: 600gr of soap per month; 1 cooking set; 1 impregnated mosquito net 4.5. Food and Nutrition Communal kitchens will be organized as an immediate emergency measure where necessary. 4.6. Security and Protection. Sites will be planned and managed in such a way that they do not trigger any gender based violence (GBV) or fire disaster hazards. Beneficiaries will be involved in the management of the sites to enhance site security and hygiene (cleaning and vector control) 4.7. Site (Camp) management The overall management of the sites will be the primary responsibility of the Ministry of Community Development and Social Services through the local Council. The responsible authority will ensure that services are delivered according to agreed standards in a coordinated manner. For information sharing and to avoid duplications coordination meetings will be held at regular intervals agreed to by all stakeholders in the camp. These will be chaired by the Chair person of the DDMC (DC) 5.0. Implementing Agencies � Department of Resettlement � International Federation of the Red Cross( IFRC) � Zambia Red Cross � United Nations High Commission for Refugees � United Nations International 37 � International Organization for Migration (IOM) 6.0. Activities 6.1. Activities to be undertaken before an Emergency No. Activities Main actor Supported by By when 1. Sensitization of DDMCs DMMU DMCF members Immediate 2. Site selection and planning DMMU DOR/IFRC/ZRC S; WFP; UNHCR December 2009 3. Assessment of available NFIs to know what resources are available and where DMMU DOR; IFRC/ZRCS; UNICEF; UNHCR December 2009 4. Identify implementing partners: tentative allocation of responsibilities is agreed DMMU DOR; IFRC/ZRCS; IOM Immediate 5. Procurement/ Propositioning of supplies DMMU DOR; IFRC/ZRCS; WFP; IOM January 2008 6. Training on Site planning and management DMMU/ DOR;IFRC/ZRC S; UNHCR; IOM December 2007 7 Periodic review of the sector response plan to update it based on the changes in the scenarios and the planning assumptions DMMU DOR; IFRC/ZRCS; UNHCR; IOM Every 2 months 8 Defining criteria for shelter needs identification and family/household’ items distribution DMMU/ DDMCs DOR;IFRC/ZRC S; UNHCR; IOM Immediate 6.2. Activities to be undertaken during an Emergency No. Activities Main Actor Supported by By when 1 Assess household needs and resources. Establish numbers requiring assistance and groups with special needs DMMU through DDMC DOR;; Local administration IFRC/ZRCS; UNHCR; WFP; IOM Immediate 2 Decide on household items required for families and individuals DMMU through DDMC DOR;Local administration IFRC/ZRCS; UNHCR; WFP; IOM Immediate 3. Provision of household items Concerned NGO, UNHCR, UNICEF Local administration; IFRC/ZRCS; NGOs Immediate 4. Site management DDMC Local administration; ZRCS; IOM 38 6.3. Activities to be undertaken after the emergency No. Activities Main Actor Supported by By when 1. In-depth assessment DDMU/ DDMCs DOR; Provincial administration; IFRC/ZRCS; NGOs After 2 month 2. Identification of resettlement area DDMU/ DDMCs DOR; Provincial administration; IFRC/ZRCS; NGOs After 2 months 3. Mobilise resources for resettlement DDMU/ DDMCs DOR; Provincial administration IFRC/ZRCS; NGOs After 2 months 4. Road Infrastructure development in the newly established settlements DMMU/ RDA DOR, Exec Director RDA, After 2 months 5. Evaluation of the implementation of the resettlement plan DDMU/ DDMCs DOR;Provincial administration; IFRC/ZRCS; NGOs After 6 months 39 7.0 Budget Items Units Shelter Requirements for up to 2 weeks Shelter requirements for 2 to 8 weeks Shelter Requirements for more than 8 weeks Total quantity Units Unit Price in USD Total Cost in USD (US$1=ZMK4500) Total Cost in ZMK Households Quantity Households Qty Households Qty Site selection 9 sites in 9 districts 761 2 2,662 7 2,662 7 9 places 1,500.00 13,500.00 60,750,000.00 Used clothes 1 bale/10hh 761 76 2,662 266 2,662 266 342 Bale 158 54,036.00 243,162,000.00 20Ltr fordable containers 1 piece/household 761 761 2,662 2,662 2,662 2,662 3,423 Bale 1 3,423.00 15,403,500.00 Fuel (Charcoal) 1bag/household/ month 761 761 2,662 5,324 2,662 5,324 11,409 Bag 13 148,317.00 667,426,500.00 Fuel (Kerosene) 4Ltr/ household /month 761 3044 2,662 21,296 2,662 21,296 45,636 Litres 1 45,636.00 205,362,000.00 Lamps for lighting 1piece/household 761 761 2,662 2,662 2,662 2,662 3,423 Piece 4 13,692.00 61,614,000.00 Mosquito nets (ITN) 3pieces/ household 761 2,283 2,662 7,986 2,662 7,986 10,269 Piece 7 71,883.00 323,473,500.00 Cooking sets communal (Kitchen for 500 families)) 1 piece for 1000 households 761 1 2,662 3 2,662 3 4 Piece 4,286.00 17,144.00 77,148,000.00 Cooking sets (family) 1set/ household 761 761 2,662 2,662 2,662 2,662 3,423 Piece 15 51,345.00 231,052,500.00 Bathing Soap (0,25kg) 1.5Kg/ household / month 761 1141.5 2,662 7,986 2,662 7,986 17,114 Kg 1 17,113.50 77,010,750.00 Detergents 1 kit /15 households 761 51 2,662 355 2,662 178 584 Kit 39 22,773.40 102,480,300.00 Cleaning materials 1 kit /20 households 761 38 2,662 266 2,662 133 437.2 Kit 66 28,855.20 129,848,400.00 Hand Tools 1 kit /20 household 761 38 2,662 133 2,662 133 171 Kit 66 11,286.00 50,787,000.00 TOTAL COST 499,004.10 2,245,518,450.00 40 Annex 3: Health and Nutrition 1.0 Planning Assumptions In an event of a flood occurring, it will be assumed that health facilities located in the flooded areas will be inaccessible and thus access adequate health services to its catchment population. The catchment population of the flood afflicted health facility will most likely seek medical attention from other nearby health facilities that are accessible to it. There is also the likelihood of a flood afflicted health facility’s catchment population being resettled in an area with no pre-existing health facility or access to a pre-existing health facility. These factors will need to be taken into consideration when deciding the number of people that will be affected by the floods, the type of health services that will be disrupted, the interventions needed and where logistics are to be pre-positioned or buffered. The criteria used to identify the population that will most likely be affected in the 2008/2009 season is as follows I. Health facilities that are located within a radius of 5km from the river bank and/or major wetlands have been deemed to be in a flood risk area. These centres have been identified by using their geographical location (GPS points). II. Health facilities located in low lying areas (valley areas) which are prone to flash floods have similarly been identified by GPS. III. Districts that were adversely affected by floods in the 2007/08 season have been included. 546,045 persons representing 91,008 households will be affected by the floods in 16 districts. Of this number there are 25,307 expectant mothers and 97,302 under 5 children. The affected population will need medical supplies to be pre-positioned/buffered in a health facility that has been identified for the purpose. As a result of floods or drought, some victims will suffer from cholera or dysentery which will require medical attention. Increase in malaria cases is anticipated due to the due to floods. It is assumed that the drugs that are currently available in the health facilities may not be adequate in responding to any form of disasters. During emergencies /disasters, movement of people in search of a livelihood is inevitable. As such, preventable diseases are normally on the increase especially in children under five years, communicable and non communicable diseases among the older population. Mental and social problems are normally a concern in such situations. This calls for intensive immunization for children under five years, intensive health promotion in the affected areas and building capacity in health providers in the area of managing emergencies/disasters. The District Health Management Teams (DHMT) as part of the District Disaster Management Committee will play a key role in the coordination, monitoring and distribution of medical supplies at district level. Health centres and hospitals will be the main implementers of health care activities. Coordination with other sectors is paramount in order to ensure that all the needs (water and sanitation, Infrastructure, transport, food etc.) are met. Community participation will be encouraged. 2.0. Overall Objectives The overall goal is to provide health care to the affected population in order to prevent and reduce excess mortality and morbidity due to floods/drought; and promote a sustainable healthy life. 41 2.1. Specific objectives The specific objectives are as follows: 1. To reduce the risk of secondary hazards e.g. epidemic. 2. To ensure adequate health care is provided to vulnerable groups. 3. To reduce impacts of diseases among the affected population. 4. To provide reproductive and child health services in disaster affected areas. 5. To provide information, education and communication on communicable and non communicable diseases. 6. To provide ART services in disaster afflicted areas. 3.0. Requirements 3.1. Scenario 1 – Floods During floods in Zambia the number of cases of malaria, diarrhoea, and upper respiratory infection are expected to increase. There is also the possibility of plague outbreaks. There is a general need to strengthen disease surveillance and response during floods. It is expected that about 546,045 adults and children number of people will need medical attention for prevention and control of diseases. It will be essential to preposition vaccines to ensure the continuation of immunization programmes. Special attention will be needed to vulnerable groups such as pregnant women, children under 5 years and PLWHA. The provision of ART services for those already on treatment is flood afflicted areas is of utmost importance to ensure adherence. The provision of ITN’s to pregnant women and children under 5 years of age is expected to safe guard against the expected increase in malaria cases. The continued control of rodents is to be carried out in collaboration with other sectors. 3.2. Scenario 2 – Cholera Zambia has been experiencing cholera outbreaks since 1991 and this is always a common occurrence during the rainy season. The contaminated water and poor hygiene are contributory factors to outbreaks of cholera. It is expected that approximately 91,008 households will be vulnerable to cholera out break in the 2007/08 rainy season. They will be a need for the cholera prone district s to pre-designate at least one health centre as a cholera treatment centre and pre position the necessary supply of fluids and cholera drugs. 4.0. Implementing Agencies � Africare � CARE � Ministry of Agriculture and Cooperatives � Ministry of Education � Ministry of Health � Ministry of Local Government and Housing � UNICEF � USAID � World Health Organisation 42 5.0. Health Activities Before, During and After the Emergency 5.1. Activities to be undertaken before an Emergency No. Activity Main Actor Supported by By When 1. Conduct a drug and inventory and identify gaps MoH WHO, NGOs November 2. Strengthen NEPPC&MC,DMMU coordination and communication DMMU/MoH MoH, Collaboratin g Partners December 2008 3. Improve the information management to capture data from the districts MoH MoH, Collaboratin g partners November 2008 4. Preposition drug requirements MoH MoH/WHO/ UNICEF November 2008 5. Community sensitization on personal hygiene, safe drinking water, MoH MoH, UNICEF, WHO, Africare, Care, Oxfam, Concern etc Ongoing 6. Map out inaccessible areas in the districts MoH DDMCs, MoE, MACO,NGOs Nov-Dec 2008 7. Environmental Manipulation to prevent outbreaks MLGH/MACO/MOH CP’s nad NGO’s Nov 2008- continuous 43 5.2. Activities to be undertaken During an Emergency No. Activity Main Actor Supported by By When 1. Inform about disease outbreaks MoH MoH, WHO, UNICEF, NGOs 24 hrs 2. Conduct assessment and report back to provincial -national level on medical requirements DMMU/MoH DDMC, NGOs, WHO, UNICEF 72 hrs 3. Mobilize resources (drugs, water, medical supplies etc) DMMU/ MoH MoH, WHO, UNICEF, NGOs, USAID 1 week 4. Coordinate the distribution of drugs and medical supplies DMMU, MoH UNICEF, NGOs, USAID 1 week 5 Mobilize medical teams MoH DDMC, NGOs, WHO, UNICEF December 08 5.3. Activities to be undertaken after an Emergency No. Activity Main Actor Supported by By When 1 Support integrated disease surveillance and reporting (IDSR), especially measles and polio surveillance. MoH MoH, WHO, UNICEF, NGOs, USAID April - December 09 2 Health education to communities (on good hygiene practice, waste disposal, etc). MoH MoH, WHO, UNICEF, NGOs, USAID Through out the year 3 Technical supervision and support visits MoH MoH, WHO, UNICEF, NGOs, USAID Dec-June 09 4 Support sustained delivery of essential health services such as immunization, child growth monitoring, maternity, HIV/AIDS, TB including through outreach where appropriate. MoH MoH, Collaborating partners, NGOs Dec 07 –June 09 5 Support the provision and distribution of essential drugs, vaccines and supplies including mosquito nets. MoH MoH, WHO, UNICEF Collaborating partners, NGOs Dec –Jan 09 44 6.0 Summary of the Budget No. Activity Resource Requirement 1 Support the provision and distribution of essential drugs, vaccines and supplies. 89,072,332.58 2 Support sustained delivery of essential health services such as immunization, child growth monitoring, maternity, HIV/AIDS, TB, ART including through outreach where appropriate. 200,036,000.00 3 Staff refresher training for prevention and control of flood related medical conditions (emergency triage, diarrhoeal diseases, plague, etc). 300,000,000.00 4 Support integrated disease surveillance and reporting (IDSR), especially measles and polio surveillance. 50,000,000.00 5 Health education to communities (on good hygiene practice, waste disposal, etc). 150,000,000.00 6 Technical Supervision and Support visits 100,000,000.00 7 Environmental Manipulation 150,000,000.00 8 Screening and provision of therapeutic supplements 51,500,000.00 GRAND TOTAL 1,090,608,332.58 45 Annex 4: Water and Sanitation 1.0. Planning Assumptions The 2008/09 floods are likely to affect 32 districts in 8 provinces; 6 in Western, 5 in N/Western, 1 in Luapula, 3 in Lusaka, 3 in Eastern, 4 in Central, 2 in the Copperbelt and 8 in Southern provinces. The floods will cause some amounts of destruction to education, health and road infrastructure. It will also affect water and sanitation systems and cause social economic disruptions as well as displacement of populations. Approximately 699,678 adults and children will be affected and in need of various WASH interventions, including hygiene education to prevent WASH-related disease outbreaks due to the 2008/09 floods. It is also expected that approximately 91,008 households will be vulnerable to cholera outbreaks in the 2008/09 floods. Out of the 699,678 people affected, it is assumed that 15,972 persons or 2,662 households will be displaced in 9 districts in need of temporal shelter and will also require water supply, sanitation facilities (bathing, latrines and hand washing) and hygiene education and supplies for various periods during flooding and immediately after the floods. Over 374 Schools are projected to be affected in 27 districts, representing over 155,000 school children needing water supply, sanitation facilities and hygiene promotion interventions. The schools will need restoration of water supply by repair or rehabilitation, provision of Chlorine and 20 litre jerry cans with lids for classroom level water treatment and storage. They will also need construction of child-friendly and gender-segregated sanitation facilities and provision of soap for hand washing to prevent disease. For emergency water supply needs, the likely intervention will be to supply water to affected communities for the first one (1) or two (2) weeks using water bowsers while permanent water solutions are put in place. Assuming all the 15,972 Internally Displaced People affected by the 2008/09 floods are considered for boreholes, a total of 56 boreholes are required although the distance to water points of 500 meters has not been considered. However, 54 boreholes have been planned for in this case. Other means or sources of water supply using bowsers will be considered depending on the prevailing disaster phase. 2.0 Overall Objective The overall objective of the sector response plan is to reduce mortality and morbidity cases due to WASH-related diseases triggered by the envisaged floods in Zambia through the provision of safe water and sanitation services to the affected population. 2.1. Specific Objectives The specific objectives for WASH sector/ cluster are the following;: i. To ensure safe and reliable access to water supplies of appropriate quality to meet the health and hygiene needs of the affected populations. ii. To ensure easy access to proper and adequate sanitation (in terms of excreta disposal and solid waste management). This will take into consideration appropriate hygiene and drainage facilities for the affected people. 46 iii. To ensure the affected populations are properly informed on WASH related behaviour practices (in the context of the emergency) through hygiene promotion to reduce the risk of disease outbreaks and eventual loss of life due to floods iv. To ensure sector/cluster coordination including regular monitoring and evaluation of the WASH emergency response and re/planning of the WASH situation of the risky and affected populations, including identifying and estimating population in need of water and sanitation. v. To ensure that patients at health centers and children in schools in the disaster affected areas have access to safe water, sanitation and appropriate hygiene facilities. 3.0. Scenario Building Projections Tables Variable Expected Events/Effects over the next 6 Months Time Frame Assumptions If any Water system/ sources submerged or damaged Inaccessibility or limited access to water sources for use of the affected populations During Floods People are forced to move and/ or use risky water sources Sanitation facilities submerged or damaged Inaccessibility or limited access to sanitation facilities for use of the affected populations During Floods Open defecation and fecal contamination of environment and water sources Contamination of water/water sources due to floods Outbreak of WASH-related diseases (including malaria, cholera, diarrhoea, etc.) in the affected areas During Floods Limited supply of WASH materials /necessities Health to distribute mosquito nets Effects Effects on WASH Direct Effects Indirect Effects Inaccessibility or limited access to water sources for use of the affected populations Use of contaminated water sources and congestions at existing facilities Use of contaminated water, failure to practice improved hygiene practices Walking long distances to collect water. People at risk of WASH-related diseases Inaccessibility or limited access to sanitation facilities for use of the affected populations Loss of dignity, congestions at existing facilities and rampant open defecation Rampant open defecation Contamination of the environment with faecal matter. People at risk of WASH-related diseases Outbreak of WASH related diseases (including malaria, cholera, diarrhoea, etc.) in the affected areas Morbidity and mortality Loss of productivity and funds due to WASH –related diseases Reduced well-being and increased poverty and deprivation 4.0 WATER & SANITATION REQUIREMENTS 4.1. Site identification and planning Site identification and planning will be done according to the sphere standards. A minimum of 35 sq meters will be provided to each individual for accommodation and day to day activities. It is worth noting that family members will be encouraged to stay near each other. 47 4.2. Water Supply Water collection points will be in a maximum distance of 500 m from each shelter and will provide at least 15 litres of water per person per day. When necessary each household will be provided with at least two 20 litres containers with lids for safe water collection, treatment (with chlorine) and storage. It may also be necessary to provide each family with a 30 litres bucket. 4.3. Sanitation To ensure proper and adequate excreta disposal, an average of one latrine hole or toilet seat will be available for 20 persons for displaced communities. For the non displaced communities, promotion of one family one latrine construction will be done. The distance between the shelters, the water collection points and the latrines will be at least 30 m. Adequate hygiene promotion and vector control activities will be done on a regular basis in collaboration with the Health Sector/ Cluster with the full participation and involvement of the displaced populations. 5.0 ACITIVITIES TO BE UNDERTAKEN 5.1. Before the Emergency Pre-position of WASH emergency preparedness and response supplies including chlorine and/or water purification tablets in the disaster/flood prone districts before the emergency starts. # Activities Coordinating Agency Lead Agency Supported by 1. Repair of machinery and equipment including vehicles, generators, measurement instruments etc DMMU MEWD MLGH, 2. Pre-positioning of bowsers and or bladders DMMU MLGH MEWD, UN system, NGOs 3 Pre-positioning of the dewatering pumps for pumping water from depressions DMMU MEWD MLGH, NGOs 4 Assessment of water resources (including flood forecasting) and estimate of people and other assets likely to be affected DMMU MEWD MLGH, CSO, MCDSS, NGOs 5. Procurement/ Pre-positioning of water treatment chemicals and field water testing kits DMMU MLGH MOH, UN system, NGOs 6. Establishing WASH Sector/cluster information management system and updating of the who what-where components DMMU MLGH UN system, NGOs 5.2. During the Emergency During the emergency, efforts will be done to restore access to safe water supply and sanitation in communities, health centers and schools. This will be done through repair/rehabilitation of water sources, water bladders and supply of jerry cans to needy populations for safe transportation from water distribution points and other sources and storage of drinking water at home, health centers and schools. # Activities Coordinating Agency Lead Agency Supported by 1. Inter Sector/Cluster Assessments of the WASH situation carried out (both rapid and comprehensive) DMMU MEWD MLGH, UN System, NGOs 2. Water supply using bowsers and bladders or DMMU MEWD MLGH 48 # Activities Coordinating Agency Lead Agency Supported by emergency tanks 3. Construction and repair/rehabilitation of water supply points (e.g., boreholes, shallow wells, etc) DMMU MLGH MEWD, MOE, MOH, MCDSS, UN system, NGOs 4. Health and hygiene education campaigns to the affected populations DMMU MLGH MOH, MEWD, UN system, NGOs 5. Construction and repair/rehabilitation of sanitation facilities in affected areas DMMU MLGH MCDSS, MOH, MOE, UN system, NGOs 6. Pumping out water in settlements that are flooded DMMU MEWD MLGH, NGOs 7. Water testing, distribution and application of chemicals for water treatment (at water sources, health centers, schools , household , etc) DMMU MEWD MOH, MLGH, CSO, MCDSS, UN system, NGOs 5.3. After the Emergency The WASH Sector/cluster will support the restoration of access to water and sanitation facilities in affected communities, including schools (construction and rehabilitation of latrines, wells, pumps, hand washing stands and storage facilities). This will include the provision of support in order to prepare community and institutional level action plans for restoration of WASH services. # Activities Coordinating Agency Lead Agency Supported by 1. Construction and repair/ rehabilitation of water points including boreholes and shallow wells in affected areas DMMU MLGH MEWD, MCDSS, MOE, MOH, UN system, NGOs 2. Construction and repair/ rehabilitation of sanitation facilities in affected areas DMMU MLGH MCDSS, MOH, MOE, UN system, NGOs 3. Assessment of water resources and water supply and sanitation services DMMU MEWD MLGH, NWASCO, CUs 4. Expansion/rehabilitation of water and sewage treatment works DMMU MLGH MOH, Cus 5. Provision of support in order to prepare community and institutional level action plans for restoration of WASH services DMMU MEWD MLGH, UN system, NGOs 6. Improve the drainage systems and long-term solid waste disposal mechanisms MLGH LOCAL AUTHORITI ES CONTRACTORS 7. Monitoring and evaluation of the sector response plan DMMU MEWD MLGH 5.4. RESPONSIBILITIES AND DUTIES For emergency response coordination and planning, it will be necessary to identify, collect and use information on WASH sector (institutional arrangements (i.e. who is doing what and where) at different levels, maps and reports 1. The District Disaster Management Committee (DDMC) will be responsible for facilitating emergency response at district level while implementation of the response will done through the district WASH team. 2. At the onset of the disaster, the district level WASH team from the DDMC will carry out own rapid and needs assessment which will then be submitted to the Regional/Provincial DMC who will report to DMMU at national level. They will work in conjunction with the satellite committees to assess the damage to water supply and sanitation infrastructure (such as hand pumps, pit latrines, etc in communities, resettlement camps, in schools and health centers) and will look out for possible back up or sharing arrangements with other districts. 49 For effective response planning, coordination and response, it will be necessary to identify key local resource people and/or institutions with special knowledge and skills on water, sanitation and hygiene. 6.0 Budget Activity/Item Cost Assessments of emergency water & sanitation needs 152,000,000 Drilling equipment maintenance/ rehabilitation 150,000,000 Water resources assessment 150,000,000 WASH co-ordination, monitoring and evaluation, and logistics 200,000,000 Provision of emergency water supply by tracking 500,000,000 Procurement and provision of temporary water sources and storage containers. 500,000,000 Procurement and supply of water testing kits 100,000,000 Supply of chlorine and/or water purification tablets 800,000,000 Construction and repair/replacement of wells, boreholes or pumping units 8,000,000,000 Provision of emergency sanitation services being used at temporary shelters 550,000,000 Construction and repair/ rehabilitation of damaged sanitation facilities 1,300,000,000 Procure and distribute pitking/fatking enzymes and labour for dosing 100,000,000 Promotion of improved solid waste management and drainage 100,000,000 Program Support to information dissemination on how to protect health 500,000,000 Community hygiene promotion meetings facilitated by CHW, EHTs , etc 400,000,000 Procurement and distribution of water quality test kits, Clorin, HTH, soap, etc 950,000,000 Capacity development/training for local Communities, EHTs, CHWs, etc 180,000,000 Support to prepare local level action plans for restoration of WASH services 480,000,000 Total 15,112,000,000 50 Annex 5: Education 1.0. Planning Assumptions In an event of a flood occurring, it is assumed that schools located in the flooded areas will be inaccessible and thus unable to support learning and teaching for the catchments population. The catchment population of the flood affected school facilities will most likely opt to use school facilities that are accessible to it in adjacent non flood affected districts. There is also a likelihood of flood affected school catchments population being resettled in an area with no pre-existing school facility. These factors will need to be taken into considering when projecting the number of schools that will be affected by flood, the type of schools that will be disrupted, the type of interventions needed and where relief facilities will be pre-positioned. The criteria used to identify the schools and population that will most likely be affected in the 2008-2009 season is as follows: � School facilities that are located within a radius of 5km of a river bank and/or wetland area which has been categorized as a flood risk area. Their actual geographical locations were used to locate the schools (GPS points). � School facilities located in low lying areas (valley areas) have also been identified using their geographical locations (GPS points). � In an event of a flood occurring, 35% of the schools will be at risk and 4% of these will flood in the 26 districts. It is anticipated that teaching and learning will be disrupted for at least three weeks. � In an event that schools are not flooded but the surrounding community is flooded, the school buildings shall be used for sheltering the community for at least three weeks during the flood. � In an event that both the surrounding areas and the schools are flooded, the school catchment population shall be required to be shifted to higher ground. � In an event that schools are submerged and buildings damaged such that pupils and teachers are not able to have access to the school, it is assumed that the school shall not be accessible for at least three weeks. The Ministry of Education has assessed the impact of the floods and prioritized interventions as immediate, medium and long term to enable the pupils and teachers to continue learning and teaching, respectively. 2.0 Overall Objective The overall objective is to provide compliant shelter and limited facilities to aid the school to function during the period of the floods. 2.1. Specific Objectives � To secure moveable equipment and assets to secure areas for safe keeping. � To provide temporally accommodation for teachers and their families for a period up to three weeks of the floods. � To provide temporally classrooms and latrines at a ratio of 1:20 persons. � To provide learning materials i.e. school in a box kits at a rate of 2 units per school. � To provide safe drinking water as per UN guidelines. 51 � To repair damaged school buildings, which might require minimal repairs at an estimated cost of K20 Million per school. � To liaise with DDMC to provide support and temporally accommodation for members of the community that may seek shelter in the school. 3.0. Temporal School Infrastructure and Learning Materials Ministry of Education will be the lead in the identification of suitable higher ground for shifting and construction of temporal shelters for classrooms, houses for teachers and their families including latrines. Learning materials in the form of school in a box and recreational kits shall be provided. Portable drinking water shall also be provided per pupil including teachers and their households. 4.0. Implementing Agencies � Catholic Secretariat � Ministry of Education � UNICEF � World Food Programme 5.0. Site (Camp) Management The Ministry of education shall manage the site and shall liaise with District Disaster Management Committees at district level. 6.0. Activities 6.1. Activities to be undertaken before an emergency No. Activities Main Actor Supported By When 1 Form committees and appoint focal point officers at all levels to lead MOE Immediate 2 Sensitization of DDMCs MOE UNICEF, WVI,WFP Catholic secretariat Immediate 2 Make agreements with other partners about roles and coordination of areas of emergency response MOE UNICEF, WVI,WFP Catholic secretariat Immediate 2 Site selection and planning MOE DDMC January 2009 3 Identify implementation partners MOE UNICEF, WVI,WFP Catholic secretariat Immediate 4 Procurement/preposition of supplies MOE UNICEF, WVI,WFP Catholic secretariat January 2009 5 Defining criteria for shelter needs MOE UNICEF, WVI,WFP Catholic secretariat immediate 6 Training on site planning and management MOE DDMC, UNICEF, WVI,WFP, Catholic secretariat January 2009 6.2. Activities to be undertaken during an Emergency No. Activities Main Actor Supported By When 1 Carryout rapid assessment to determine the immediate needs MOE DDMC January 2009 2 Identification of actual schools affected MOE DDMC Late January 2009 3 Assess the needs and design solution MOE UNICEF, WVI,WFP Catholic secretariat January 2009 4 Provide necessary equipment and materials to construct temporally shelters MOE UNICEF, WVI,WFP Catholic secretariat January & February 2009 52 5 Shift the affected schools to identified safe sites MOE DDMC January & February 2009 5 Provide safe water and temporally latrines, Provide chlorine MOE UNICEF, WVI,WFP Catholic Secretariat January & February 2009 6 Provide school in a box and recreational kits MOE UNICEF January & February 2009 7 Construct temporally classrooms and latrines MOE DDMC January & February 2009 8 Assess how the plan is working and make necessary changes to improve the situation MOE UNICEF, WVI,WFP Catholic secretariat February & March 9 Periodical monitoring to review situation on the ground to make corrections if need be. MOE UNICEF, WVI,WFP Catholic secretariat March 6.3. Activities to be undertaken After an Emergency No. Activities Main Actor Supported By When 1 Demobilize and shift school back to original place MOE DMMC April/May 2 In-depth assessment MOE, UNICEF, WVI,WFP Catholic secretariat May 3 Evaluation of the implementation plan. MOE UNICEF, WVI,WFP Catholic secretariat May 200 4 Carryout rehabilitation works on all school infrastructure damaged by floods. MOE May 200 ACTIVITIES RESOURCE REQUIREMENT [ZMK] 1. Site selection and planning 150,000,000.00 2. Identify implementation partners 1,000,000.00 3. Procurement/preposition of supplies 500,000,000.00 4. Defining criteria for shelter needs 25,000,000.00 5. Training on site planning and management 80,000,000.00 6. Assess the needs and design solution 20,000,000.00 7. Provide necessary equipment and materials to construct temporally shelters 250,000,000.00 8. Shift the affected schools to identified safe sites 700,000,000.00 9. Provide safe water and temporally latrines, Provide chlorine 200,000,000.00 10. Construct temporally classrooms and latrines 350,000,000.00 11. Assess how the plan is working and make necessary changes to improve the situation 40,000,000.00 12. Periodical monitoring to review situation on the ground to make corrections if need be 200,000,000.00 13. In-depth assessment 55,000,000.00 14. Evaluation of the implementation plan 41,000,000.00 15 . Provide school in a box and recreational kits 3,500,000,000.00 16 Carryout rehabilitation works on all school infrastructure damaged by floods 4,500,000,000.00 TOTAL BUDGET 10,612,000,000.00 53 Annex 6: Agriculture and Food Security Sector 1.0. Planning Assumptions The areas assumed to most likely be affected are those located within five (5km) buffer from the river banks and main wetlands areas which have been categorized as flood risk areas. The anticipated floodwaters will most likely affect crops in the riverine areas due to inundation of floodwaters. Furthermore the crops planted in low lying areas are likely to be swept away by flash floods. Pasture for animals is likely to be reduced as much of it will be inundated causing livestock to be unthrift, more prone to diseases with a reduced capacity for draught power. Unrestricted livestock movement due to limited pasture areas may precipitate the outbreak and spread of some livestock diseases such as Foot and Mouth Disease (FMD). This will affect people’s livelihoods and food security status eroded as floods take their toll causing populations to be displaced. It is also anticipated that most plateau areas within agro-ecological zone IIa and IIb (semi arid as well as eastern and central plateau areas) where the soil water holding capacity are low will result into heavy leaching of soil nutrients causing crops to start yellowing. The expected damage to crops and market infrastructure will most likely cause food insecurity and increased vulnerability to hunger. Furthermore, the rising food and fuel prices will exacerbate the food insecurity situation. The contingency plan will aim at providing relief food amounting to 29,142 MT of cereals to an estimated population of 699,678 people (116,613 households) directly affected by floods to safeguard their household food security. Affected households that have access to viable wetlands will also need to be supported with inputs to undertake dry season cropping (winter cropping). Lessons learnt from the floods that occurred in 2007/08 rainy season indicated that farmers who practiced conservation farming techniques were able to minimise the impact of the flood on the crops as compared to those who did not. The flood prone areas especially those that are proximal to game parks have an interface with wild animals (due to competition of grazing land) known to carry the FMD pathogen. It is estimated that 500,000 cattle (representing 50,000 HH) will require vaccination from transmissible diseases such as Contagious Bovine Pleuro pneumonia (CBPP) and FMD. The threat of CBPP spread is imminent in areas of Western, North Western and part of Southern province. Wet conditions may also pre-dispose livestock to some diseases, such Foot rot, H. Septicaemia and increased endo-parasitic loads. In the event of a disease outbreak in flood affected areas, Government is expected to bear the cost for most of the vaccinations (300,000 cattle representing 30,000 HH), but will require supplementary assistance to contain the spread of the disease. Supplementally efforts to control the disease would target 200,000 cattle for an estimated 20,000 cattle owning HH in flood affected areas. 54 2.0. Overall objective The overall objective will be to provide awareness on flood mitigatory measures to populations likely to be affected by floods in the country so as to reduce the impact on food security. 2.1. Specific Objectives � To restore agricultural production capacities of flood affected Households through provision of emergency input support � To carry out emergency livestock vaccinations and treatments in order to control possible disease outbreaks this may be pre-disposed by flood conditions and the mass movement of animals as well as people. 3.0. Scenario Building Projection Table Variable Expected Events/Effects over the next 7 months Time Frame Maize Available � Declining availability of stocks at household level. � Increasing dependency on markets in adjacent high producing figures. November 08- February 09 Maize Price � Increased prices expected earlier than normal. � Increased flow of commodities from surplus to deficit areas. � Increased flow of food commodities from surplus countries (i.e. Malawi, Mozambique) December 08 – February 09 � Emerged crops swept away by floods � Surviving crops wilts due to excess water � Surviving crop yellows and stunts due to nutrient leaching � performance � Crop failure due to poor rains in the Nyika plateau. November 08- January 09 Crops � Reduced harvest as a result of poor crop April 09 – June 09 Livestock � Unrestricted movement of livestock and people resulting in outbreak of transmissible livestock diseases such as FMD and CBPP � Reduced drought power due unthrift conditions of the cattle November 08– March 09 Agricultural Input prices � Increased input prices due to increasing oil prices and cost of raw materials. October 08 – December 08 Rural infrastructure � Bridges and roads rendered impassable resulting in inability by farmers to access agriculture inputs such as seed and fertilizers. � Reduced access to markets December 08– February 09 55 Effects Table Effects Effects on Households Indirect Effect Declining availability of stock � Collecting unusual amounts of wild foods � Increased out migration � Reduce expenditure on non essential commodities � Food insecurity at household level � Increased livestock sales � Reduced availability of labour � Increased vulnerability Maize price increase earlier than normal � Increased livestock sales to purchase maize � Collecting unusual wild foods � Increased out migration � Reduce expenditure on non essential commodities � Food insecurity at household level � Early on-set of hunger period � Diversion of money from productive assets to fund consumption � Increased numbers of sex workers Reduced harvest � Low stock levels � Food insecurity at household level � Reduced production capacity � Reduced household income � Increase in non farming activities � Increased vulnerability Outbreak of transmissible livestock diseases � Reduced drought power � Reduced household income � Food insecurity at household level � Increased vulnerability � Reduction in number of available coping options Increased agricultural input prices � Reduced purchase capacity � Reduced hectarage to planted crops � Reduced crop production and productivity � Increase in non agricultural activities Damage to roads/bridges � Reduced access to agricultural inputs � Reduced access to markets � Increase in transportation costs � Transporters shun affected area � Reduced access to agricultural extension messages. � Food insecurity 56 4.0. Activities 4.1. Activities to be undertaken before the floods Activity Coordination Supported by whom When Implementing partner identification and Coordination and defining of roles DMMU MACO/FAO October Farmer sensitization on flood mitigatory measures involving crop/variety selection and conservation farming DMMU MACO Before onset of the rains Crop monitoring DMMU MACO After planting Identification of seed and other input sources DMMU MACO/FAO October/November Surveillance of CBPP, FMD and other transmittable livestock diseases DMMU MACO Year round 57 4.2. Activities to be undertaken during the floods 4.2.1. Food Needs Table District Name 2008 Projected Population Population Affected Projected Cereal Needs (Dec 08 - Apr 09) MT Sinazongwe 109,491 21,898 912 Chavuma 38,015 9,504 396 Zambezi 83,127 20,782 866 Lukulu 86,599 17,320 721 Siavonga 71,970 10,796 450 Senanga 131,969 26,394 1,099 Gwembe 45,404 13,621 567 Lundazi 314,765 47,215 1,966 Mazabuka 260,057 78,017 3,249 Mongu 194,957 38,991 1,624 Monze 210,845 42,169 1,756 Namwala 115,251 23,050 960 Samfwa 204,609 30,691 1,278 Chama 100,584 9,081 378 Shang'ombo 86,369 17,274 719 Kazungula 88,517 22,129 922 Lusaka 1,310,273 65,514 2,729 Ndola 466,759 23,338 972 Kitwe 461,290 23,065 961 Mkushi 145,940 29,188 1,216 Serenje 175,587 35,117 1,463 Kafue 186,224 46,556 1,939 Mambwe 60,894 15,224 634 Luangwa 25,218 5,044 210 Kalabo 138,509 27,702 1,154 Total Cereal Requirement 5,113,223 699,678 29,142 Implementing Agencies � DMMU � WFP 58 4.2.2. Activities to be undertaken After the Emergency Estimated Cost Activities Coordination Supported by whom When K 000 U$ Rapid Food Security Needs assessment and area mapping DMMU VAC/WFP/MACO After floods have receded 200,000,000 44,444.44 Relief food operations DMMU WFP/NGOs After floods 32,056,200,000 7,123,600.00 Beneficiary identification and selection DMMU DDMC/MACO/NGOs/WFP After floods have receded 50,000,000 11,111.11 Dry season inputs for 10,000 HHs in 23 districts to enable cultivation of 0.25 Ha/HH DMMU MACO/FAO/NGOs March 2,930,000,000 651,111.11 Support to conservation Agriculture for 12,000 HHs to enable cultivation of 0.25 Ha/HH DMMU MACO/FAO/NGOs April 4,120,000,000 915,555.56 Inputs distribution DMMU NGOs/MACO/ WFP April 160,000,000 35,555.56 Survey of suspected livestock disease outbreaks and mapping DMMU MACO After the floods have receded 200,000,000 44,444.44 Awareness creation among livestock owners on disease prevention and control measures in affected districts DMMU MACO After survey 40,000,000 8,888.89 Procurement of vaccines and antibiotics for 500,000 cattle in 23 districts DMMU FAO/MACO After Diagnostic survey 500,000,000 111,111.11 Livestock vaccinations and treatment for cattle DMMU MACO After survey 210,000,000 46,666.67 Total 40,466,200,000 8,992,488.89 59 Annex 7: Information Management and Emergency Communications 1.0. Planning Assumptions It is anticipated that telecommunication infrastructure will be disrupted following the 2008/09 rainy season. This will to a larger extent affect information flow to the affected populations. This therefore entails that there is need to establish emergency information dissemination hubs. 2.0. Overall objective The overall objective will be to provide an efficient and effective information management and emergency communication mechanism for response. 2.1. Specific objectives � To determine the level of preparedness of communications authorities and service providers through awareness activities on the impending floods to occur in 2008/09 season. � To determine the preparedness levels of the Government Ministries, NGOs both local and international as well as UN agencies on the impending floods for the 2008/09 season. � To ensure the timely acquisition of appropriate communication equipment and expertise to improve the communication coordination during the floods. � To co-ordinate the provisions of communication operability such as the licensing, frequency allocation and the transportation where necessary of equipment for use by direct stakeholders during the period of the floods where necessary. � To disseminate timely and appropriate information to the affected populations via the print, voice and electronic media to create awareness of the Floods. � To ensure timely and credible information flow to DMMU from the affected districts for decision making by the relevant authorities and ministries. Emergency communications infra structure shall be installed as need arises and capacity built among stakeholders. Information shall flow from the districts to the national level as well as among stakeholders at the same levels. In order to achieve this, national radio and TV stations will be involved. At local level, community radio stations will be used. Traditional methods of information dissemination shall not be ignored. Standard operating procedures to be established and put in place on the use of communications equipment especially HF and VHF communications. 3.0 Implementing Organisations � DMMU � WFP � Communications Authority of Zambia 60 4.0. Activities 4.1. Activities to be undertaken Before an Emergency No. Activities Main Actor Coordinating Agency Supported By By When 1 Informing of service providers, authorities, NGO’s etc to ensure adequate preparation and maintenance of their communications equipment in the event of floods. DMMU DMMU/CAZ Voice and print media, CAZ, UN, Zamtel Immediate 2 Acquisition of Equipment necessary for adequate communications during the floods. DMMU DMMU CAZ, By 30th November 2008 3 Co-ordination of communication strategies and Equipment, Frequencies, Licensing, Request for RBGans From ITU for 5 month period. DMMU DMMU/CAZ CAZ, FPMU By 30th October 2008 4 Survey of aerial masts for installation of emergency communication equipment DMMU DMMU ZAMTEL,ZESCO,CELTEL, MTN, ZNBC Immediate 5 Floods awareness campaign DMMU DMMU ZANIS/ZNBC, Community Radio station Immediate 6 Development of data matrix by sector DMMU/UNDP DMMU NGOs, Line Ministries, UN Immediate 7 Development of 3W database and maps DMMU/UNDP DMMU NGOs, Line Ministries, UN Immediate 8 Development of Emergency Info i.e. Using PDAs to collect information. DMMU,WFP, CSO,UNDP,UNICEF DMMU/UNDP NGOs, Line Ministries, UN Immediate Installation of Emergency Communications in affected areas DMMU DMMU/CAZ UN, ZAMTEL, ZESCO, CELTEL, MTN, ZNBC By 30th November 2008 4.2. Activities to be undertaken During the Emergency No. Activities Main Actor Coordinating Agency Supported By By When 5 Installation of Emergency Communications in affected areas DMMU DMMU/CAZ UN, ZAMTEL, ZESCO, CELTEL, MTN, ZNBC By December 2008 6 Floods awareness campaign DMMU DMMU ZANIS/ZNBC, Community Radio station Immediate 7 Data Entry into data matrix by sector DMMU/UNDP DMMU NGOs, Line Ministries, UN Immediate 61 9 Request for Information Management support from the UN DMMU/UNDP DMMU NGOs, Line Ministries, UN By November 2008 4.3.. Activities to be undertaken After the Emergency No. Activities Main Actor Coordinating Agency Supported By By When Review of Telecommunications and Information Management Activities DMMU/UNDP DMMU NGOs, Line Ministries, UN By April 2009 5.0. Activities List of activities No. Activities Cost (USD) Cost (ZMK) 1 Informing of service providers, authorities, NGO’s etc to ensure adequate preparation and maintenance of their communications equipment in the event of floods. 2 Acquisition of Equipment necessary for adequate communications during the floods. 3 Co-ordination of communication strategies and Equipment, Frequencies, Licensing 4 Survey of aerial masts for installation of emergency communication equipment 5 Installation of Emergency Communications in affected areas 6 Floods awareness campaign 65,000 234,000 7 Development of data matrix by sector - 8 Development of 3W database and maps 9 Request for Information Management support from the UN - 10 Development of Emergency Info i.e. Using PDAs to collect information. 30,000 108,000,000 TOTAL 6.0. Costing of the Activities 6.1. HF and VHF Communications Equipment Radio Unit Unit Cost (USD) Total Cost (USD) Total Cost (ZMK) Solar pack, NAPS, EQP-0015-0015-IAP 6 2862 17,172 61,819,200 Motorola GM-360 VHF mobile radio kit, KMV1 11 411 4,521 16,275,600 Toolkit, EQP-0019-0026 1 4190 4,190 15,084,000 Motorola programming kit with USB to RS232 adapter cable 1 350 350 1,260,000 Cable, coaxial, 10mm, 50ohm, double shielded, Cinta CNT-400 (low loss cable), roll of 250m, Andrew, EQP-0003-0029 3 555 1,665 5,994,000 Connector, UHF/PL259 (solder), CNT-400 (low loss cable), EQP-0014-0047 20 9 180 648,000 Connector, N-FEMALE, CNT-400 (low loss cable), EQP-0014-0040 10 7 70 252,000 Connector, N-Male, CNT-400 (low loss cable), EQP-0014-0038 10 8 80 288,000 Motorola multi-charge VHF handheld radios, 1 323 323 1,162,800 62 Equipment Radio Unit Unit Cost (USD) Total Cost (USD) Total Cost (ZMK) MDHTN3004 Barrett 2050 HF mobile radio kit (950 model not longer available), incl radio antenna tuner and whip antenna 1 3332 3,332 11,995,200 Barrett HF mobile whip antenna 6 79 474 1,706,400 Motorola GM-360 with DTMF microphone, MDM25KHF9AN5AE 1 0 0 12 Volt power supply, RS-20A-BB-220E 1 240 240 864,000 Motorola GP-340 VHF handheld radio, MDH25KDC9AN3AE WVI 6 180 1,080 3,888,000 Battery, NiMH ultra high capacity for GP340 Motorola, HNN9008AR 1 32 32 115,200 Barrett 2050 HF base radio (950 model not longer available) 1 3060 3,060 11,016,000 Barrett 923 power supply for 950 HF radio 1 391 391 1,407,600 Barrett HF mobile automatic antenna tuners 3 689 2,067 7,441,200 Earthing kit, E-KIT 1 317 317 1,141,200 Rope UV resistant, nylon (200m roll), EQP 0014-0019 1 17 17 61,200 Motorola GR-500 internal power supply 1 450 450 1,620,000 Barrett 900 series remote control head (for 950 model) 1 544 544 1,958,400 Subtotal 40,555.00 145,998,000 Estimated shipment cost (15%) 6,083.25 21,899,700 7.5% Administrative cost 3,041.63 10,949,850 Total (USD) 49,679.88 178,847,550 Source – UN / WFP FITTEST (Dubai) 6.2. Satellite Communications/ Cellular Communications and SMS alerts Satellite Equipment Unit Unit Cost (USD) Total Cost (USD) Total Cost (ZMK) Thuraya Hand Held Sat Phones 30 0 To be requested from the ITU in Geneva through CAZ BGAN 700 satellite phone, EQP-0004-0034 30 0 To be requested from the ITU in Geneva through CAZ BGAN 700 satellite phone, EQP-0004-0034 10 4,351 43,510 156,636,000 Cell Phones 12 150 1,800 6,480,000 SMS Alert System 1 9,000 9,000 32,400,000 VSAT System 1.2-1.8 M dish/stand and modem. 9 3,000 27,000 97,200,000 Bandwidth 256/256 Kbs for 6 months 6 (months) 2,500 15,000 54,000,000 Transport to the Provinces 10,000 40,000,000 63 Satellite Equipment Unit Unit Cost (USD) Total Cost (USD) Total Cost (ZMK) Casual Labour for setting up the Equipment 9 300 2,700 9,720,000 VSAT Installation Costs 9 500 4,500 16,200,000 Total (USD) 113,510 412,636,000 Source of Equipment– UN / WFP FITTEST (Dubai) and ITU Geneva 6.3. Public Awareness Campaign Unit Unit Cost (USD) Total Cost (USD) Total Cost (ZMK) Community Radio Broadcasts 100 90 9000 32,400,000 Television Broadcast 100 180 18000 64,800,000 Pamphlets and Flyers 1000 1 1000 3,600,000 Mobile public announcements (ZANIS) 9 3000 27,000 97,200,000 Others 10,000 36,000,000 Total (USD) 65,000 234,00,000 6.4. Information Management Unit Unit Cost (USD) Total Cost (USD) Total Cost (ZMK) Development of data matrix by sector - - - Development of 3W database and maps - - Request for Information Management support from the UN - Development of Emergency Info i.e. Using PDAs to collect information. 100 300 30,000 108,000,000 Total 30,000 108,000,000 7.0 Summary of the Budget Summary Total Cost (USD) Total Cost (ZMK) HF and VHF Communications 49,679.88 178,847,550 Satellite Communications/ Cellular Communications and SMS alerts 113,510 412,636,000 Public Awareness Campaign 65,000 234,000,000 Information Management 30,000 108,000,000 Total 207,440.99 933,483,550 64 Annex 8: Logistics 1.0. Planning assumptions The following assumptions have been made: The logistics sector is cross cutting. Because of this, logistics ties the relief requirements in all sectors and seeks to put in measures that will ensure their movement from the source to their utility points. There will be storage at places along the supply lines. The logistics sector’s budget is based on the storage and movement of relief supplies identified above from source to utility points as stated above. It will include the costs relating to the management of those supplies whilst in transit and cost at intermediary and final warehousing facilities. The infrastructure damage ranges from moderate to high, thus making it difficult/impossible to reach certain areas by road. Major rivers in flood prone areas present a barrier to access places beyond the rivers in question. There will therefore be need to use a combination of road, air and water modes of transport in order to ensure timely delivery of relief supplies. Key sectors will play their role in capturing the changing parameters of the operation so as to allow the logistics sector adjust the operation in real time. It is for this reason that the logistics sector has in built flexibility. 2.0. Overall Objective The overall objective is to ensure efficiency and timeliness of the delivery of relief supplies in order to mount effective preparedness, response and rehabilitation interventions. 2.1. Specific Objectives � To procure and deliver the right supplies according to the sectors’ requirements � To source and distribute the right quantities of supplies to avoid waste of resources and delayed response � To provide the supplies in the right order to minimise the impact of gaps in the pipeline on the populations that will be affected � To ensure that relief supplies are in good condition � To ensure the relief supplies are delivered at the right place � To ensure the relief supplies are procured and delivered at the right time. 3.0. Implementing Organisations � DMMU � Transporters (Rail, Air and Road) � NGOs � Suppliers 65 4.0. Budget Activities Cost(ZMK) Cost(US$) 1 Transportation of Maize grain(by road) 11,085,616,800 2,463,470.40 2 Distribution of grain 10,199,700,000 2,266,600.00 3 Airlifting of relief supplies 2,030,568,000 451,237.33 23,315,884,800 5,181,307.73 66 Annex 9: Detailed Sector Resource Gap Analysis Sector Activity Resource Required (ZMK) Resource Available (ZMK) Net Resource Requirement (ZMK) Emergency infrastructure Technical assessment 450,000,000.00 0 450,000,000.00 Review of performance of various structures after floods 200,000,000.00 0 200,000,000.00 Identification of remedial needs and intervention methods for damaged infrastructure 150,000,000.00 0 150,000,000.00 Prioritization of damaged road infrastructure/ bridges 100,000,000.00 0 100,000,000.00 Generate cost estimates and mobilize resources 100,000,000.00 0 100,000,000.00 Road Infrastructure Bridges/Roads emergency repairs 10,000,000,000.00 600,000,000.00 9,400,000,000.00 Subtotal 11,000,000,000.00 600,000,000.00 10,400,000,000.00 Site selection 60,750,000.00 12,400,000.00 48,350,000.00 Used clothes 243,162,000.00 0 243,162,000.00 20Ltr fordable containers 15,403,500.00 0 15,403,500.00 Fuel (Charcoal) 667,426,500.00 54,000,000.00 613,426,500.00 Fuel (Kerosene) 205,362,000.00 0 205,362,000.00 Lamps for lighting 61,614,000.00 0 61,614,000.00 Mosquito nets (ITN) 323,473,500.00 0 323,473,500.00 Cooking sets - communal (Kitchen for 500 families)) 77,148,000.00 0 77,148,000.00 Cooking sets (family) 231,052,500.00 0 231,052,500.00 Bathing Soap (0,25kg) 77,010,750.00 0 77,010,750.00 Detergents 102,480,300.00 0 102,480,300.00 Cleaning materials 129,848,400.00 0 129,848,400.00 Human Settlement and Shelter Hand Tools 50,787,000.00 6,461,633.00 44,325,367.00 Subtotal 2,245,518,450.00 72,861,633.00.00 2,172,656,817.00 Support the provision and distribution of essential drugs, vaccines and supplies. 89,072,332.00 0 89,072,332.00 Support sustained delivery of essential health services such as immunization, child growth monitoring, maternity, HIV/AIDS, TB, ART including through outreach where appropriate. 200,036,000.00 0 200,036,000.00 Health and Nutrition Staff refresher 300,000,000.00 0 300,000,000.00 67 Sector Activity Resource Required (ZMK) Resource Available (ZMK) Net Resource Requirement (ZMK) training for prevention and control of flood related medical conditions (emergency triage, diarrhoeal diseases, plague, etc). Support integrated disease surveillance and reporting (IDSR), especially measles and polio surveillance. 50,000,000.00 0 50,000,000.00 Health education to communities (on good hygiene practice, waste disposal, etc). 150,000,000.00 0 150,000,000.00 Technical Supervision and Support visits 100,000,000.00 0 100,000,000.00 Environmental Manipulation 150,000,000.00 0 150,000,000.00 Screening and provision of therapeutic supplements 51,500,000.00 50,000,000.00 1,500,000.00 Total 1,090,608,332.00 50,000,000.00 1,040,608,332.00 Assessments of emergency water & sanitation needs 152,000,000 0 152,000,000.00 Drilling equipment maintenance/ rehabilitation 150,000,000 0 150,000,000.00 Water resources assessment 150,000,000 0 150,000,000.00 WASHE co ordination, monitoring and evaluation, and logistics 200,000,000 0 200,000,000.00 Provision of emergency water supply by tracking 500,000,000 0 500,000,000.00 Procurement and provision of temporary water sources and storage containers. 500,000,000 100,000,000 400,000,000.00 Procurement and supply of water testing kits 100,000,000 50,000,000 50,000,000.00 Supply of chlorine and/or water purification tablets 800,000,000 300,000,000 500,000,000.00 Water and Sanitation Construction and 8,000,000,000 0 8,000,000,000.00 68 Sector Activity Resource Required (ZMK) Resource Available (ZMK) Net Resource Requirement (ZMK) repair/replacement of wells, boreholes or pumping units Provision of emergency sanitation services being used at temporary shelters 550,000,000 0 550,000,000.00 Construction and repair/ rehabilitation of damaged sanitation facilities 1,300,000,000 0 1,300,000,000.00 Procure and distribute pitking/fatking enzymes and labour for dosing 100,000,000 0 100,000,000.00 Promotion of improved solid waste management and drainage 100,000,000 0 100,000,000.00 Program Support to information dissemination on how to protect health 500,000,000 0 500,000,000.00 Community hygiene promotion meetings facilitated by CHW, EHTs , etc 400,000,000 0 400,000,000.00 Procurement and distribution of water quality test kits, Clorin, HTH, soap, etc 950,000,000 300,000,000 650,000,000.00 Capacity development/trainin g for local Communities, EHTs, CHWs, etc 180,000,000 0 180,000,000.00 Support to prepare local level action plans for restoration of WASH services 480,000,000 0 480,000,000.00 Sub Total 15,112,000,000 750,000,000 14,362,000,000.00 Site selection and planning 150,000,000.00 150,000,000.00 Identify implementation partners 1,000,000.00 1,000,000.00 Procurement/preposi tion of supplies 500,000,000.00 0 500,000,000.00 Defining criteria for shelter needs 25,000,000.00 25,000,000.00 Education Training on site 0 69 Sector Activity Resource Required (ZMK) Resource Available (ZMK) Net Resource Requirement (ZMK) planning and management 80,000,000.00 80,000,000.00 Assess the needs and design solution 20,000,000.00 20,000,000.00 Provide necessary equipment and materials to construct temporally shelters 250,000,000.00 250,000,000.00 Shift the affected schools to identified safe sites 700,000,000.00 0 700,000,000.00 Provide safe water and temporally latrines, Provide chlorine 200,000,000.00 0 200,000,000.00 Construct temporally classrooms and latrines 350,000,000.00 100,000,000.00 250,000,000.00 Assess how the plan is working and make necessary changes to improve the situation 40,000,000.00 40,000,000.00 Periodical monitoring to review situation on the ground to make corrections if need be 200,000,000.00 0 200,000,000.00 In-depth assessment 55,000,000.00 55,000,000.00 Evaluation of the implementation plan 41,000,000.00 41,000,000.00 Provide school in a box and recreational kits 3,500,000,000.00 0 3,500,000,000.00 Carryout rehabilitation works on all school infrastructure damaged by floods 4,500,000,000.00 3,000,000,000.00 1,500,000,000.00 Subtotal 10,612,000,000.00 3,682,000,000.00 6,930,000,000.00 Rapid Food Security Needs assessment and area mapping 391,000,000.00 100,000,000 291,000,000.00 Relief food operations 32,056,200,000.00 0 32,056,200,000.00 Beneficiary identification and selection 161,000,000.00 50,000,000.00 111,000,000.00 Dry season inputs for 10,000 HHs in 23 districts to enable cultivation of 0.25 Ha/HH 2,930,000,000.00 0 2,930,000,000.00 Agriculture and Food Security Support to conservation Agriculture for 12,000 HHs to enable cultivation of 0.25 0 70 Sector Activity Resource Required (ZMK) Resource Available (ZMK) Net Resource Requirement (ZMK) Ha/HH 4,120,000,000.00 4,120,000,000.00 Inputs distribution 160,000,000.00 0 160,000,000.00 Survey of suspected livestock disease outbreaks and mapping 200,000,000.00 0 200,000,000.00 Awareness creation among livestock owners on disease prevention and control measures in affected districts 40,000,000.00 0 40,000,000.00 Procurement of emergency vaccines and antibiotics 400,000,000.00 217,065,644.00 182,934,356.00 Emergency vaccinations and treatment 160,000,000.00 0 160,000,000.00 Subtotal 40,466,200,000 367,065,644.00 40,099,134,356.00 HF and VHF Communications 178,847,550.00 178,847,550.00 0 Satellite Communications/ Cellular Communications and SMS alerts 412,636,000.00 90,652,450.00 321,983,550.00 Public Awareness Campaign 234,000,000.00 0 234,000,000.00 Information Management and Emergency Communication Information Management 108,000,000.00 0 108,000,000.00 Subtotal 933,483,550 269,500,000 663,983,550.00 Logistics Transportation of Maize grain(by road) 11,085,616,800.00 0 11,085,616,800.0 0 Distribution of grain 10,199,700,000.00 0 10,199,700,000.0 0 Airlifting of relief supplies 2,030,568,000.00 0 2,030,568,000.00 Subtotal 23,315,884,800.00 0 23,315,884,800.00 GRAND TOTAL 104,775,695,138.00 5,791,427,277.00 98,984,267,855.00 71 Annex 10: Disaster Risk Reduction (DRR) Sector Focal Point Persons INSTITUTION NAME and Phone No POSITION 1 Ministry of Agriculture & Cooperatives Mrs. Mulemwa A. Sitwala 250169/ 0977842522 Director-Cooperatives Dept. 2 Ministry of Works and Supply Ms. Bupe Kaonga 0977118930 Director-Planning & Monitoring Dept. 3 Ministry of Community Development & Social Services Mr. Henry Nkhoma 0977776311 Director-Community Dev. Dept 4 Ministry of Defence Mrs. Clementine Miti Sakala Director-Research, Planning & Projects 5 Ministry of Education Dr. Felix Phiri 254342 Director-Planning & Information 6 Ministry of Home Affairs Emmanuel Nguni Director-Research, Planning & Projects 7 Ministry of Energy & Water Development Mr. Christopher Chileshe Assistant Director 8 Ministry of Communications & Transport Mr. Maurice Muchinda 251912/ 0966758337 Director – Meteorology 9 Ministry of Finance & National Planning Mr. Patrick H. Choolwe 0977877559 Assistant Director 10 Ministry of Health Dr. Velepi Mtonga 0966430848 Director-Technical Support Services 11 Ministry of Mines & Minerals Development Mr. Mooya B.C. Lumamba Ag. Director-Mines Safety Dept. 12 Ministry of Local Government & Housing Mr. Davis C. Zulu 0955881661 Assistant Director Infrastructure & Support Services 13 Ministry of Tourism, Environment & Natural Resources Mr. E.M. Shitima 0977893961 Principal Environment and Natural Resources Officer 14 Ministry of Information and Broadcasting Services