Directing the Establishment of the Policy and Administrative Framework for Offshore Wind Development (Executive Order No. 21)
颁布于 2023-04-19 · 文本截至 2026-10-01
以研究形式发布的公开法律与官方指引,不构成法律、税务或金融建议。
研究内容本身以英文撰写。标题和标签已翻译,调查结果和引文未翻译。
关于这部法律
- 语言
- English
- 类型
- 条例
- 国家
- 菲律宾
- 主题
- Energy
- 关键词
- legal proceedings/administrative proceedings, renewable energy
在哪里阅读
该法律没有记录来源链接。
文本
所收录的法律原文,按条款排列。每个条款都有自己的链接。
Section 1. Definition of Terms. For the purpose of this Order, the following terms shall mean: a. "Grid" - the high voltage backbone system of interconnected transmission lines, substations and related facilities. b. "OSW Development Activities" - activities that must be undertaken to completely develop an OSW Project. c. "OSW Projects" - projects for the exploration, development, and utilization of OSW resources for power generation. d. "Permitting Agencies" - agencies of the Government or relevant entities that are concessionaires or franchisees of the Government which permitting process or authority is relevant to or required for the development of OSW Projects. The list of Permitting Agencies is attached as Annex A.
Section 2. Policy and Administrative Framework. Within sixty (60) days from the issuance of this Order, the Department of Energy (DOE) is hereby directed to formulate and issue a Policy and Administrative Framework for the efficient and optimal development of the country's OSW resources, which shall be made applicable to all Permitting Agencies.
Section 3. Permits for OSW Development Activities. All Permitting Agencies shall within sixty (60) days from the effectivity of this Order, submit to the DOE a comp lete list of appropriate permits required by relevant Permitting Agencies, including all requirements, fees, and procedures for the issuance thereof. Subject to applicable laws, rules and regulations, the Department of the Interior and Local Government (DILG) shall submit to the DOE a complete list of appropriate permits required by local government units (LGUs), includ ing the requirements, fees and procedures for the issuance thereof, within sixty (60) days from the effectivity of th is Order. Not later than fifteen (15) days from receipt of confirmation by the DOE that the list is complete and proper for integration into the Energy Virtual One-Stop Shop (EVOSS) platform, the DILG shall disseminate to concerned LGUs the standard list of permits for OSW Development Activities.
Section 4. EVOSS Integration. Within thirty (30) days from receipt of submission of the complete list made under Section 3 hereof, the DOE shall review the subm ission and take the appropriate action on whether they shall: (a) initiate the full integration of applicable permit into the EVOSS platform, provided that all requirements have been submitted ; or (b) require the Permitting Agency to remediate or supplement a deficient or incomplete submission. Upon the integration of a Permitting Agency's requirements or process into the EVOSS platform, the processing of such Permitting Agency's permit shall be done through the EVOSS platform in compliance with RA No. 11234.
Section 5. Compliance with EVOSS Time Frames. All Permitting Agencies are directed to ensure the efficient and timely processing of permits. All Permitting Agencies are directed to strictly observe applicable time frames for the issuance of permits under RA No. 11234 and its Implementing Rules and Regulations.
Section 6. Rationalization of Fees. All Permitting Agencies are directed to review their existing fees and charges for permits, and to update them in accordance with applicable laws, rules and regulations, with a view of supporting and encouraging the development of OSW Projects.
Section 7. Transmission. The DOE shall coordinate with the National Grid Corporation of the Philippines and National Transmission Corporation to ensure timely development of the needed Grid interconnection facilities of OSW Projects for the dispatch of electric power to the Grid.
Section 8. Agency Support. All concerned national government agencies and instrumentalities, including government-owned or-controlled corporations, and LGUs, are hereby directed to provide the necessary assistance and support to the DOE for the successful implementation of this Order.
Section 9. Implementing Guidelines. Within thirty (30) days from the issuance hereof, the DOE shall issue the guidelines necessary to implement this Order, which shall include, among others, an enumeration of the OSW Development Activities.
Section 10. Separability. If any part or provision of this Order shall be held invalid or unconstitutional, the provisions not affected thereby shall remain in full force and effect.
Section 11. Repeal. All orders, rules and regulations, and other issuances or parts thereof which are inconsistent with the provisions of this Order are hereby repealed or modified accordingly.
Section 12. Effectivity. This Order shall take effect immediately. DONE, in the City of Manila, this 19th day of April in the year of our Lord Two Thousand and Twenty-Three . By the President: • Office of the President MAI..ACANANG RECORDS OFFICE CER'flFIED COPY 1 ril.~\~ E. FmOUMO-WD 111ii,nn ff 1iniiii mrn11 q- ui -'}GV~ DIRECTOR IV PBBM001886 ANNEX A LIST OF PERMITTING AGENCIES Permitting Agencies shall include, but are not limited to, the following: a. Department of Agrarian Reform ; b. Department of Agriculture: i. Bureau of Fisheries and Aquatic Resources; c. Department of Environment and Natural Resources: i. Biodiversity Management Bureau; ii. Environmental Management Bureau; iii. Forest Management Bureau; and iv. Land Management Bureau; d. Department of Justice; e. Department of Labor and Employment; f. Department of National Defense; g. Department of Public Works and Highways; h. Department of Trade and Industry; i. Department of Transportation: i. Civil Aviation Authority of the Philippines; ii. Maritime Industry Authority; iii. Philippine Coast Guard; and iv. Philippine Ports Authority; j. Bureau of Customs; k. Bureau of Immigration; I. Bureau of Internal Revenue; m. Bureau of Quarantine; n. Energy Regulatory Commission; o. National Commission on Indigenous Peoples; p. National Grid Corporation of the Philippines; q. National Mapping and Resource Information Authority; r. National Power Corporation; s. National Transmission Corporation; and t. Power Sector Assets and Liabilities Management Corporation.