  1. 13. Medical facilities and first aid services. 14. Protection against dangerous parts of machinery. 15. Training inexperienced workers.

  2. 16. I nstructions on emergency procedures. 17. Reporting of accidents.

  3. 18. Inquiries into accidents.

  4. 19. Monthly statements on production, etc. 20. Annual report.

  5. 21. Books, records, etc., to be made available to the Director.

  6. 22. Special reports.

  7. 23. Construction of plants, etc.

  8. 24. Storage tanks.

  9. 25. Entry into storage tanks, etc.

  10. 26. Operational safeguards in relation to storage tanks.

  11. 27. Disposal of residues, sludges, rusts, etc.

  12. 28. Storage tanks to be calibrated.

  13. 29. Storage of liquified petroleum gases.

  14. 30. Construction and spacing of tanks.

  15. 31. Disruption to continuous operation.

  16. 32. Abandonment or replacements of any plant. 33. Pressure vessels. 34. Non-pressure vessels.

  17. 35. Handling and blending of dangerous additives and chemicals.

  18. 36. Storage capacities.

  19. 37. Spare parts.

  20. 38. Spillage in the refinery.

  21. 39. Analysis of imported stock for use in the refinery.

  22. 40. Samples and specimens.

  23. 41. Samples and specimens: control of export.

  24. 42. Fires and explosions.

  25. 43. Refinery effluent and drainage disposal.

  26. 44. Office and working accommodation. 45. Offences. 46. Fees.

  27. 47. General power to issue directions, etc.

  28. 48. Interpretation.

  29. 49. Short title. SCHEDULE PETROLEUM REFINING REGULATIONS [LN. 45 of 1974.] under section 9 [22nd July, 1974) [Commencement.] PART I Procedure relating to establishment, etc., of refinery

  30. 1. Form of applicati on for licence to construct or operate a refi nery, etc. (1) Application for a licence to construct or operate a refinery shall be made to the Minister and shall be in Form A in the Schedule to these Regulations. [Form A. Schedule.] (2) Every such application shall be accompanied by at least three copies of a detailed study of the project and the prescribed fee which shall not be refundable.

  31. 2. Li cence to construct or operate a refi nery A licence to construct or operate a refinery shall be in Form B in the Schedule to these Regulations and may be granted subject to such terms and conditions as the Minister may prescribe. [Form B. Schedule.]

  32. 3. Enl arg ement or mo di ficati on of existi ng refinery (1) No changes shall be made in the installations of a refinery with a view to in- creasing its capacity except with the prior approval in writing of the Minister and upon payment of the prescribed fee. (2) Application to enlarge, alter or add to any refinery or any of the plants therein or change the normal use of the component units or plants of any refinery or part thereof when by so doing such change shall create a substantial alteration to the capacity of the said refinery for processing crude oil and related products shall be in Form C in the Schedule to these Regulations and shall be accompanied by the prescribed fee which shall not be refundable. [Form C. Schedule.]

  33. 4. Appoi ntment of a manager (l) Work in condition with the construction and operation of a refinery shall be con- ducted under the direction of a manager who shall have continued charge of all opera- tions authorised by the licence under which he is operating. (2) Every licensee shall notify the Director in writing of the name and address of the manager and of any subsequent changes thereof. PA RT II Duties of a Manager: General

  34. 5. Manag er to ensure compliance with provisions of regul ati ons It shall be the duty of the manager to ensure that the provisions of these Regulations are fully complied with in relation to his refinery.

  35. 6. Appoi ntment of competent pers ons The Manager shall appoint in writing competent persons for the purpose of general supervision of all operations in the refinery including all aspects of construction, mainte- nance and refining and shall submit for the approval of the Director each appointment and subsequent changes.

  36. 7. Observance of g ood refini ng practices Where no specific provision is made by these Regulations for any aspect of the con- struction, operation and maintenance of a refinery, practices conforming with interna- tional standards shall be observed subject to the approval of the Director.

  37. 8. Refinery areas to consti tute restricted areas (1) All refinery areas shall constitute restricted areas, the boundaries of which shall be clearly defined as specified in regulation 9 of these Regulations. (2) Only persons authorised by the manager shall be admitted into such restricted areas.

  38. 9. Erecti on of fences (1) Adequate and secure boundary fencing shall be provided around all restricted areas, tank farms, products' offtake facilities and the jetty; and access to these areas shall be through recognised entrances so controlled as to prevent the entry of unauthorised persons and vehicles. (2) All vehicles shall be confined to approved routes within the refinery area except in regard to special cases where specific vehicles are authorised by the manager to devi- ate from such approved routes.

  39. 10. Obs ervance of fire and safety reg ulati ons (1) A competent person shall be responsible for ensuring the observance of all fire and safety precautions within restricted areas. (2) There shall be provided to the satisfaction of the Director, adequate means de- signed to extinguish fire and to control effectively the spread of fire and explosions. (3) A central fire station shall be provided with suitable equipment and manned by personnel who can immediately proceed to the scene of a fire or explosion and effectively make use of the available equipment to put the fire or explosion under control. (4) Each item of the fire fighting equipment shall be inspected and tested at appropri- ate intervals by a competent person appointed for the purpose, and the last date of such inspection shall be painted on the appliance and the result of such inspection shall be en- tered in a log book specially kept for that purpose, all such entries shall be duly signed by the competent person. (5) Operational personnel employed in the refinery area shall be instructed in the use of fire fighting equipment. Instructions to personnel in case of fire shall be clearly and concisely expressed in writing and prominently displayed. (6) Easy access to strategic points for mobile equipment shall be provided and shall at all ti mes be kept free. (7) The manager shall ensure that no person smokes or ignites any fire or flame in any refinery area except in places set aside for the purpose. (8) Except with the permission of the manager no person shall have in his possession while he is in any refinery area any matches or mechanical lighters or similar devices or any lamp or light or any ignited or ignitable matter. (9) Whenever a fire or explosion occurs in a refinery area the competent person in the tire station shall be informed immediately and steps shall be taken to extinguish the tire and control further explosion.

  40. 11. Warni ng notices (1) "No Smoking" signs shall be conspicuously displayed in restricted areas. (2) Warning notices regarding the prohibition of entry by unauthorised persons, naked lights and other hazards shall be conspicuously displayed. Safety and health of persons

  41. 12. S afety cl othing and appli ances (1) The manager shall provide, for all persons working in the refinery areas in con- nection with crude oil or any refined product, suitable protective clothing, equipment and appliances of a pattern approved by the Director. (2) The manager shall instruct all workers on the importance and use of safety cloth- ing and appliances issued to them and shall enforce their use. He shall make arrange- ments to ensure that equipment is always kept in good condition. (3) Quick-operating automatic water showers ready for instant use and tested daily shall be provided in the vicinity of caustic vessels and pumps and in such other appropri- ate accessible places as the Director may, from time to time, direct. (4) Eye-wash bottles and automatic fountains shall be located in strategic and con- spicuous locations in the refinery area.

  42. 13. Medical faciliti es and first ai d servi ces (1) Adequate first aid and emergency medical facilities shall be provided to deal with all cases arising from any accident occurring in a refinery area. (2) First aid boxes or cupboards shall be placed under the charge of competent per- sons who shall always be readily available during working hours, and a notice shall be affixed in every work-room stating the name of the person in charge of the first aid box or cupboard provided in respect of any area and for any shift period.

  43. 14. Protection against dangerous parts of machinery All dangerous or moving parts 01" any machinery shall be securely fenced or guarded whether situated in an engine house or, not, so however that, in so far as the safety of a dangerous part of any machinery cannot by reason of the nature of the operation be se- cured by means of fixed guard, the requirements of these Regulations shall be deemed to have been complied with if a device is provided which satisfactorily warns or protects the operator from coming in contact with that part.

  44. 15. Training inexperienced workers No person shall be allowed to work with any machinery or in any process, which is li- able to cause or result in bodily injury to him or endanger his health, unless he has been fully instructed as to the danger likely to arise therefrom and the precautions to be ob- served therewith; and- (a) he has received sufficient on-the-job training on the machinery or in the pro- cess; or (b) he is under the adequate supervision of a person who has a thorough knowl- edge and experience of the machinery or process and who shall be responsible for the safety of the trainee.

  45. 16. Instructions on emergency procedures (1) The manager shall provide instructions regarding procedures to be followed dur- ing an emergency and shall ensure that each worker knows his functions under such in- structions. (2) The manager shall send a copy of such instructions and any subsequent altera- tions thereto to the Director. Accidents

  46. 17. Reporting of accidents (1) Where any accident occurs in a refinery which results in loss of life or serious injury written notice of the accident, in Form D in the Schedule to these Regulations shall forthwith be sent by the manager to the Director and copied to the nearest inspector by the manager. [Form D. Schedule.] (2) The Director may, if he so desires, order an inquiry to be held by the inspector. (3) For the purpose of this regulation, serious injury includes any injury involving the loss of or impairment in the use of any limb or other part of the body or one which results in such incapacity (whether temporary or permanent) that the sufferer is incapable of continuing the work on which he was engaged immediately before he suffered the injury. (4) A record shall be kept of all other injuries in the refinery and any such record shall be made available to an inspector on demand. (5) The provisions of this regulation shall be additional to the requirements contained in the Factories Act, Workmen's Compensation Act and the Electrical Supply Regula- tions in the case of an accident or fire involving electrical apparatus or equipment. [Cap. FI. Cap. W6. Cap. E7.]

  47. 18. Inquiries i nto acci dents (1) Any inspector holding an inquiry under this Part shall, for the purposes of the in- quiry, have power to do the following things, that is to say- (a) to summon witnesses; (b) to call for the production of relevant books and documents which may be nec- essary to ascertain whether the provisions of these Regulations have been complied with; (c) to examine any person or witness, either alone or in the presence of any other person, and to require any such person or witness to sign a declaration of the truth of the matters respecting which he is so examined; (d) to exercise such other powers as may be necessary for carrying these Regula- tions into effect. (2) A notice requiring a witness to appear at an inquiry to be held pursuant to these Regulations shall be in Form E in the Schedule to these Regulations. [Form E. Schedule.] PA RT III Reports

  48. 19. Monthl y statements on producti on, etc. (1) The manager shall forward to the Director, not later than 21 days after the end of each month, a refinery statement for the month in a form which the Director may from time to time, direct. (2) The statement shall contain- (a) a report of important occurrences, technical or otherwise, in the refinery during the month; (b) information on the duration of any shut-down and any major work done during the shut-down including information on any plant taken out of commission during the shut-down and the reasons for the work done; (c) information covering inspection report on any installation in the refinery; (d) the latest estimates of anticipated monthly production for the next three months explaining the reason or reasons for any increase or decrease in production generally or in a specific product or products; (e) a brief summary of the results of test runs, and experiments carried out during the month in the normal course of operations on any section of the refinery in- stallation.

  49. 20. Annual report Not later than two months after 31 December of every year, the manager shall for- ward to the Director three copies of an annual report reviewing the activities for the pre- vious year and details of proposed activities for the current year; and such report shall be prepared in a form acceptable to the Director.

  50. 21. B ooks, records , etc., to be made avail able to the Director The manager shall make available to the Director or to his duly authorised represen- tative such books, files and to technical data as are relevant to the technical operation of the refinery.

  51. 22. S peci al reports The Director may, from time to time, call for special reports on any aspect of the re- fining operations which mayor may not have otherwise been provided for in this Part of these Regulations. PART IV Miscellaneous

  52. 23. Constructi on of pl ants, etc. Before any plant installation or related facility under the refinery licence is con- structed or assembled for any purpose, the manager shall forward to the Director for ap- proval all relevant details regarding the design specifications, purpose and location of the plant, installation or related facility including any programme of activities prior to the commissioning of the plant, installation or related facility.

  53. 24. S torage tanks (1) All permanently placed storage tanks containing crude oil and any class of pro- duct shall be installed within a bund-wall capable of retaining the contents of the largest tank plus 10% of the remaining tanks; and where there is only one tank the capacity of such bund-wall shall be sufficient to contain the whole of the tank's contents should the tank be emptied by leakage or otherwise. (2) In addition, the tanks referred to in paragraph (1) of this regulation shall- (a) be fitted with access doors sufficiently large to enable easy access and with vents capable of relieving any excess pressure or vacuum; (b) have access to their roofs by means of a ladder or staircase of a type approved by the Director and all floating roof tanks shall have adequate wind girders; (c) have provision made for containing any leakage to prevent oil contaminating the water when located above water; and (d) be provided with efficient electrical earth connections independent of pipe connections, having an electrical resistance value not exceeding ten ohms when measured by an earth resistance tester of the "Megger" or similar type.

  54. 25. Entry i nto storage tanks, etc. (1) Before permitting workmen to enter a tank which had previously contained pe- troleum products it shall be gas freed and the concentration of gas determined, and all feed and vent lines shall be disconnected and blanked off, and tank hatches shall be kept open. (2) During tank cleaning operations adequate ventilation shall be provided inside the tank and, as work progresses, frequent tests shall be made to detect increases in gas con- centration. (3) If the gas concentration exceeds 0.05%, gas masks shall be worn, tools shall be incapable of causing sparks, and hand lamps and torches used shall either- (a) be certified tlame proof, group 11, in conformity with British Standard 229; or (b) be constructed in compliance with the United States National Electrical Safety Code and the National Board of Fire Under-Writers National Electric Code for explosion proof electrical apparatus and equipment.

  55. 26. Operati onal safeg uards in rel ati on to storage tanks The manager shall ensure, especially where any tank in operation is being tilled, that operational safeguards are used to avoid, so far as possible, exceeding the safe limit of fill applied to the particular tank under consideration.

  56. 27. Dis posal of resi dues, sludges, rusts, etc. Residues, sludges, rusts and similar matter from tanks which may have contained leaded petroleum products shall be disposed of according to good refining practices and only to such places as have been approved by the Director.

  57. 28. Storage tanks to be cali brated (1) Before a tank is used for any storage, it shall be properly calibrated in the pres- ence of an inspector or other representative of, and by a method approved by, the Direc- tor, and calibration tables on the tank shall be forwarded in duplicate to the Director by the manager. (2) If for any reason any tank which has been in use requires to be recalibrated, the calibration shall be done in the presence of an inspector or other representative of, and by a method approved by, the Director, and calibration tables on the tank shall be forwarded to the Director in duplicate by the manager.

  58. 29. Storage of li quefied petroleum g ases (1) The design, construction and testing of the liquefied petroleum gas unit and stor- age shall be in accordance with the current requirement of standard practice of design and construction. (2) The storage and handling of L.P.G. shall be in accordance with good refinery practices. (3) The standard practice of design and construction and good refinery practices re- ferred to in this regulation shall be such as are acceptable to, and approved by, the Di- rector.

  59. 30. Construction and s pacing of tanks (1) Tanks of capacity less than 500 water tons shall be sited and placed in accordance with safety considerations. Due allowance shall be made for the nature of the product stored and its volume and the characteristics of the surrounding area. (2) If the storage relates to class "A" or class "B" petroleum- (a) in normal design fixed roof tanks, the minimum distance- (i) between the perimeter of the tank and the outer body of the installation shall be the diameter of the tank or 25 metres, whichever is the greater; (ii) between tank and tank shall be the diameter of the smaller, or fifteen metres, whichever is less; (b) in floating roof tanks, the minimum distance- (i) between the perimeter of the tank and boundary of the installation; or (ii) between tank and tank shall be not less than fifteen metres; and (c) for the purposes of sub-paragraphs (a) and (b) of this paragraph, small tanks shall be considered as one tank if sited together in groups not exceeding a combined capacity of 3,000 water tons, and spaced according to the require- ments of the locality and of operational needs. (3) If the storage relates to liquefied petroleum gases, the minimu m distance- (a) from the boundary of the installation; or (b) from open fires; or (c) from class "A" and class "B" petroleum, shall not be less than forty-five metres. (4) A list of tanks, their gross capacities and their use shall be forwarded by the man- ager to the Director. If for any reason other than that of a production emergency a tank is to be altered in use, for a purpose different from that for which it was designed, the Di- rector shall be informed before such alteration is effected, and if for any reason whatso- ever a tank is to be altered in construction, the approval of the Director shall be obtained before such alteration is effected.

  60. 31. Disrupti on to continuous operati on (1) The manager shall notify the Director on Form F in the Schedule to these Regu- lations not less than thirty days before any planned shut-down. [Form F. Schedule.] (2) The manager shall on the occurrence of any operational incident resulting in the shut-down of the refinery or any part thereof or resulting in putting out of use of any plant, machinery or installation or on the occurrence of any other emergency resulting in such shut-down or putting out of use, forthwith notify the nearest inspector in writing of the occurrence stating- (a) the reasons for the shut-down or putting out of use, its estimated duration and its possible effect on the production commitment of the refinery; and (b) the steps, if any, the manager has taken or proposes to take to avoid a recur- rence of the incident or circumstances that give rise to the shut-down or putting out of use.

  61. 32. Aban donment or repl acements of any pl ant Before any plant is permanently put out of commission, the Director shall first be in- formed on Form F in the Schedule to these Regulations, and his written approval ob- tained. [Form F. Schedule.]

  62. 33. Pressure vessels (1) All pressure vessels in use in the refinery shall be of good construction, sound materials and adequate strength and shall be properly maintained in accordance with standards acceptable to the Director. (2) Every pressure vessel shall be periodically inspected in accordance with the ap- plicable provisions of the Factories Act and, in particular, the following matters shall be carried out- [Cap . Fl.] (a) oil heaters shall be inspected not more than eighteen months from their first commissioning and thereafter at intervals of thirty months and the fire tubes replaced when below the minimum thickness, and at the same time, other parts and fittings both internal and external shall be inspected; (b) all compressed-air receivers shall be drained of liquid daily- (i) where the internal surface of the receiver cannot be inspected and in any event not less often than once in every thirty months the receiver shall be tested hydraulically to the recommended test pressure; (c) gas separators shall be tested whenever the opportunity occurs but at intervals not exceeding 36 months, and they shall be pressure tested to a pressure in ex- cess of its working pressure in accordance with the code of design and con- struction of the vessels; (d) relief valves and safety valves shall- (i) be inspected at least once in every thirty months or at such shorter in- tervals as shall be necessary to maintain them in satisfactory condition and to ensure that they operate effectively as soon as the safe working pressure is exceeded; (ii) be set to operate at a pressure not exceeding 10% above the working pressure and shall pass full design quality at this setting, and where ap- propriate, bursting discs may be used in lieu of safety valves; (iii) be stamped or tagged with their set popping pressure. (3) Every pressure vessel shall be fitted with tested pressure gauge, graduated in the metric system, and such gauge shall be checked for accuracy at regular intervals. (4) All new pipework shall be tested in accordance with the code of design and con- struction before being put into service, and shall also be similarly tested whenever any alteration or repair has been carried out. (5) In this regulation, the expression "pressure vessel" includes steam boilers, steam receivers and steam containers, air receivers and their attachments and lifting appliances.

  63. 34. Non-pressure vessels (1) Heat exchangers, processing vessels and other equipment used in the refinery shall be inspected from time to time in accordance with an inspection code acceptable to the Director. (2) If any fault is detected during the course of inspection a detailed report of inspec- tion shall be forwarded to the Director.

  64. 35. Handli ng and blendi ng of dangerous addi ti ves and chemi cals (l) Tetraethyl lead, tetramethyl lead or any other dangerous additives and chemicals shall be handled strictly and in accordance with the up-to-date instructions as drawn up by the manufacturers, a copy each of which shall be forwarded to the Director and in- spector. (2) The amount of lead which one imperial gallon of any finished product shall con- tain may not exceed that which is acceptable in current good refinery practice and in any case shall not exceed that amount which the Director may, from time to time, specify. (3) If the result of any sample which an inspector or an officer delegated by the Di- rector withdraws and analyses in the presence of an officer delegated by the manager shows that the approved maximum has been exceeded at any time, the manager shall be guilty of an offence under these Regulations and shall be liable on conviction to a fine of N l00 or imprisonment for six months.

  65. 36. Storag e capaci ties (1) The total storage capacities for finished products in any refinery shall not be less than thirty days of the maximum processing capacities of the refinery. (2) The storage capacity for any feedstock, additive or chemical shall be such as to satisfy at least thirty days' requirement.

  66. 37. S pare parts (l) The manager shall ensure ready availability of spare parts for critical equipment. (2) "Critical equi pment", for the purpose of this regulation, means any equipment which if taken out of commission will endanger the life of, or lead to a shut-down of, the refinery or parts thereof.

  67. 38. S pill age in the refinery (1) Any unprogrammed spillage, of crude, products or chemicals inside the refinery shall immediately be notified to the inspector. (2) Such notice shall be followed within seven days after the spillage shall have oc- curred by a written report describing the cause and nature of the spillage, the amount of spillage and the method of estimating it, the amount of spillage recovered, precautionary measures taken since the spillage to prevent any hazard that may arise therefrom, and precautionary measures taken to prevent such spillage in the future.

  68. 39. Anal ysis of i mported stock for use in the refi nery (1) The exact quantity of each imported feedstock, blendstock and additives and de- tails of all analysis carried out by the refinery shall be duly recorded. (2) Specimens of imports and results of any detailed analysis of such imports, carried out by the refinery shall be submitted to the Director whenever he so requires.

  69. 40. S amples and s peci mens (1) The licensee may remove for examination and analysis samples and specimens of crude oils, catalysts, petroleum products or any other materials considered necessary in course of his operations. (2) The Director shall be given full particulars of all samples and specimens so re- moved.

  70. 41. S amples and s peci mens: control of export The licensee may not export samples or specimens abroad except with the written permission of the Director and subject to such conditions as he may specify.

  71. 42. Fires and expl osi ons Where fire or explosion occurs within a refinery area a full report hereof shall be made forthwith to the nearest inspector.

  72. 43. Refinery effluent and drai nage dis pos al (1) The manager shall ensure that drainage and disposal of refinery effluent and drainage water shall conform to good refining practices, the specification of the effluent and the mode of disposal shall be subject to the approval of the Director. (2) Co mplete analyses of the effluent and drainage water shall be performed at such regular intervals as the Director may prescribe and results of such analyses shall be clearly entered in a register specially kept for that purpose, every entry of which shall be duly signed by a competent person. (3) The manager shall adopt all practicable precautions including the provision of up- to-date equipment as may be specified by the Director from time to time, to prevent the pollution of the environment by petroleum or petroleum products; and where such pollu- tion occurs the manager shall take prompt steps to control and, ifpossible, end it. (4) An inspector or an officer authorised by the Director may withdraw samples of any effluent and drainage water at any time for analysis and if the result of such analysis reveals that the approved specifications have not been complied with the manager shall be guilty of an offence under these Regulations and shall be liable on conviction to a tine of N 100 or imprisonment for a term of six months.

  73. 44. Office and working accommo dati on The manager shall provide on the refinery premises such office and other working ac- commodation for an inspector as may be specified by the Director.

  74. 45. Offences (1) If any person- (a) contravenes any provision of these Regulations; or (b) fails to comply with any direction of the Director given in exercise of any of the powers conferred under these Regulations; or (c) fails to comply with the terms of any warning notice displayed pursuant to these Regulations, he shall be guilty of an offence and liable on conviction to a tine of NIOO or imprison- ment for a term of six months. (2) Any person who fails or refuses- (a) to appear as a witness following a summons to do so issued by an inspector under regulation 18 of these Regulations; or (b) to produce any book or document required to be produced by an inspector for the purposes of an inquiry under regulation 18 of these Regulations, shall be guilty of an offence and liable on conviction 10 a fine of NI 00 or imprisonment for a term of six months. (3) Where a statement, information or report made or recorded pursuant to these Regulations includes any untrue statement the manager shall, unless he proves that he had reasonable grounds to believe that the statement was true or proves that he did not authorise the making or recording of the untrue statement, be guilty of an offence and liable on conviction to a fine of N 100 or imprisonment for a term of si x months. PA RT V Supplemental

  75. 46. Fees The following fees shall be payable- [S.1. 2 of 1996.] (a) on application for a refiner's licence ...................................................... . US $50,000 (b) on the issue of a refiner's licence ............................................................ . US $100,000 (c) on the 31 st December following the issue of the licence and on every 31 st December thereafter- for every 2,000 tons, or part thereof, of the maximum crude oil capacity or hydro-carbon feed which the refinery is designed to process per calendar year .................................................................... . N IOO,OOO.OO (d) an application to modify a refinery or any of its installations ............. . N IOO,OOO.OO

  76. 47. General power to issue directi ons, etc. (1) The Director may, from time to time, give directions as to the manner of compli- ance with any matter provided for under these Regulations. (2) The Minister may, from time to time, issue instructions on any matter concerning the construction, efficient operation and maintenance of a refinery.

  77. 48. Interpretati on In these Regulations, unless the context otherwise requires- "cl ass' A' petroleum" includes all hydrocarbon liquids having a flash point below 73 of, by Abel closed cup test, and all petroleum stocks with a flash point below 200 of that are being handled at temperatures above their flash point; "cl ass 'B' petrol eum" includes all hydrocarbon products having tlash points from 73 OF to 150 OF inclusive; "cl ass ' C' petroleum" includes all hydrocarbon products having tlash points above 150 O F; "competent person" means a person appointed, with the approval of the Director, by the manager in writing as a reliable person capable of exercising overall general supervi- sory responsibility in ensuring compliance with the provisions of these Regulations or parts thereof; "crude oil " means mineral oil in its natural state before it has been refined or treated (excluding water and other foreign substances); "Di rector" means the Director of Petroleum Resources, Ministry of Petroleum Re- sources, and includes any person for the time being holding, acting or performing the functions of that office; "fl ash-poi nt" means the degree of temperature at which petroleum gives off a flam- mable vapour upon being tested by either the Abel closed cup tester or the Pensky- Martens closed tester; "i ns pector" means a petroleum engineer, any petroleum engineer above that rank, or any other officer appointed in writing by the Director to perform any or all of the duties prescribed in these Regulations; "leade d refi ned product" means any refined product to which a portion of lead has been added in any form, with the aim of improving the qualities of the refined product; "licensee" means the holder of a refining licence issued pursuant to the Act and these Regulations; "L.P. G." or "li quefi ed petroleum g as" means any petroleum product which is gas at normal atmospheric temperature and pressure comprising mainly of butane or propane or admixtures thereof and, being liquefiable under pressure is normally stored and handled as a liquid; "manag er" means the person appointed manager pursuant to regulation 4 of these Regulations;