Electricity Supply (Amendment) Act 2024

颁布于 2024-07-02 · 文本截至 2026-10-01

以研究形式发布的公开法律与官方指引,不构成法律、税务或金融建议。

研究内容本身以英文撰写。标题和标签已翻译,调查结果和引文未翻译。

关于这部法律

语言
English
类型
法令
国家
马来西亚
主题
Energy
关键词
energy conservation/energy production, governance, sustainable use

在哪里阅读

文本

所收录的法律原文,按条款排列。每个条款都有自己的链接。

  1. 1. (1) This Act may be cited as the Electricity Supply (Amendment) Act 2024. (2) This Act comes into operation on a date to be appointed by the Minister by notification in the Gazette. Amendment of long title

  2. 2. The Electricity Supply Act 1990 [Act 447], which is referred to as the “principal Act” in this Act, is amended in the long title by deleting the words “and the efficient use of electricity”. Amendment of section 4

  3. 3. Section 4 of the principal Act is amended— (a) in paragraph (k), by deleting the words “efficient use of electricity,”; 4 Laws of Malaysia Act A1739 (b) in the English language text, in paragraph (ga), by substituting for the word “efficient” the word “effective”; and (c) by deleting paragraph (la). Amendment of section 11

  4. 4. Subsection 11(1) of the principal Act is amended by substituting for the word “efficient” the word “effective”. Deletion of Part Va

  5. 5. The principal Act is amended by deleting Part Va. Amendment of section 53

  6. 6. Subsection 53(1) of the principal Act is amended by deleting paragraphs (xa), (xj) and (xk). Saving and transitional

  7. 7. (1) Any application for and issuance of, a Certificate of Approval in respect of the efficient use of electricity under the principal Act which is pending on the date of the coming into operation of this Act shall be deemed to have been made and shall be dealt with by the Commission under the relevant provisions of the Energy Efficiency and Conservation Act 2024 [Act...]. (2) Any Certificate of Approval in respect of the efficient use of electricity which has been issued under the principal Act and is in force immediately before the date of coming into operation of this Act shall, on the date of the coming into operation of this Act, be deemed to have been issued under the Energy Efficiency and Conservation Act 2024 and shall remain valid until the Certificate of Approval is expired or revoked by the Commission. Electricity Supply (Amendment) 5 (3) Any energy performance testing report, made in respect of the efficient use of electricity under the principal Act immediately before the date of coming into operation of this Act shall be deemed to have been validly made under the Energy Efficiency and Conservation Act 2024 and remain valid for the period of five years from the date of the report or until the report is revoked by the Commission. (4) Any notice, order or prohibition issued by the Commission in respect of the efficient use of electricity immediately before the date of coming into operation of this Act shall, on the date of coming into operation of this Act, be discontinued. (5) Any action, seizure, prosecution or proceedings taken, made, commenced or pending in respect of the efficient use of electricity immediately before the date of coming into operation of this Act shall, on the date of coming into operation of this Act, be continued as if the principal Act had not been amended by this Act. (6) Any provision in the subsidiary legislation made under the deleted paragraphs 53(xa), (xj) and (xk) of the principal Act shall remain in operation until revoked or replaced by the subsidiary legislation made under the Energy Efficiency and Conservation Act 2024.