Executive Order No. 460 to establish the National Policy for Public Private Parternship Governance and Transparency Procedure

Made 2021-09-03 · Text as of 2026-10-01

Public law and official guidance, published as research. Not legal, tax or financial advice.

About this law

Language
English
Kind
Regulation
Country
Palau
Subjects
General
Keywords
governance, policy/planning, public private partnership (PPP), public procurement

Where to read it

    No source link is recorded for this law.

Text

The law's own text, section by section, as held. Each section has its own link.

  1. 1. Defining PPP itself and its Contractual Structure, classifying PPP inherent traits, and identifying PPP project attributes, and;

  2. 2. Assessing projects suitable for PPP procurement and selecting the best PPP model that is likely to achieve the best value for money outcome for the Government. and;

  3. 3. Governing PPP arrangements by: (i) setting forth responsibilities for the Ministry of Finance; (ii) establishing Special Units such as a PPP Unit and Debt Management Unit; (iii) developing PPP Framework under Presidential Directive No. 21-47; (iv) developing and procuring PPP projects; and (v) managing and formally executing PPP contracts; and

  4. 4. Providing tenets and PPP Project Teams for undertaking PPP projects and developing the maximum benefits of PPPs; and

  5. 5. Illustrating the life cycle of a PPP Project; and

  6. 6. Committing to transparency and fairness in its procurement processes and over the lifetime of PPP Projects. Se.ction 2. EE:e Transparency .Procedrne. The PPP Transp.arency..&o.cedurefor the_Republic of Palau builds upon existing legislative provisions and requirements in Palau that promote transparency of government decision-making and related processes. The PPP Transparency Procedure shall apply to all future solicited PPP projects undertaken by the Republic and its agencies, entities, and State-Owned Enterprises. It will apply to State Governments and to unsolicited proposals submitted to government agencies. For existing PPP projects or those in current procurement, elements of the Policy will be applied on a case-by-case basis. The PPP Transparency Procedure should lead to better value for money outcomes for both government and taxpayers through: (i) stronger and more competitive bidding fields, arising from increased bidder confidence in the fairness of the process and of lower perceived political risk by investors; (ii) greater focus on the quality of the tender documents and processes, given that the outcomes will be made public; and (iii) execution of more sustainable contracts, because of the resultant robustness of the process and increased community acceptance of PPPs. The Palau PPP Transparency framework is based on the following principles:

  7. 1. A commitment at the highest levels of the Republic to transparency in PPP procurement consistent with that expressed in the PPP Policy Statement.

  8. 2. A focus on procuring infrastructure projects solicited by the Republic, rather than through unsolicited proposals (USPs). With the National Infrastructure Investment Plan (1st draft December 2020 and as updated over time) being the primary basis for infrastructure projects to be solicited by the Government.

  9. 3. Preparation and publication of the details of the proposed process for use in PPP procurement (e.g. project selection, project governance, tendering, contract management, etc). The process is to be outlined in the forthcoming PPP Guideline, to be prepared following issue of the PPP Policy Statement.

  10. 4. Use of competitive tendering, including as the default approach for USPs. Using the procurement process that will be set out in the PPP Guideline.

  11. 5. Additional disclosure for USPs than for solicited PPPs during the pre-procurement and, if procured non-competitively, procurement stages. In recognition that USPs do not arise through a competitive process; the form of the additional disclosure to be set out in the PPP Guideline.

  12. 6. Ease of public access to disclosed material including the use of a single consolidated communication site-Ministry of Finance website. Additionally, portfolio agencies and/or State-Owned Enterprises may also display relevant material on their websites.

  13. 7. Establishment of relevant Government entities such as: (i) PPP Unit responsibilities will include establishment of appropriate portal on Ministry of Finance website and posting of materials, and (ii) Debt Management Unit wil assess and morutor the totalairect and contingent fiscal obligations made by the Republic, including from PPP transactions. Core to the PPP Transparency Procedure are the following specific commitments:

  14. 1. Publication of the Republic's PPP project pipeline (updated semi-annually). Using the Template set out in Attachment A of the PPP Transparency Procedure.

  15. 2. Request for Proposal (RfP) documents to outline the project agreement contents that are proposed for disclosure, post contract execution.

  16. 3. Disclosure of identity of short-listed bidders for each project to be made at time of RFP issue.

  17. 4. Disclosure of material on contracted projects, within 90 days of contract execution, or financial close as applicable using the Template set out in Attachment B.

  18. 5. An annual statement by the Republic of its total direct and contingent liabilities to include those arising from PPP projects and to be provided in annual Budget papers.

  19. 6. Projects will be open to review by the Public Auditor post-contract execution/financial close under Title 40 of the Palau National Code. The Office of the Public Auditor may undertake fmancial audits, performance audits, and program audits of any government agency (National, State, or local) that it deems appropriate and, in doing so, may access any contract to which that agency is a party (except personal employment contracts). Section 3. Effective Date and Duration. This Order shall take effect immediately and shall continue until it is rescinded or suspended. ,cl, IN WITNESS WHEREOF, I have hereunto set my hand and affixed my official seal this~ day of September 2021, at the Satellite Office in Koror, Republic of Palau. Surangel S. Whipps, Jr. esident of the Republic of Palau

Executive Order No. 460 to establish the National Policy for Public Private Parternship Governance and Transparency Procedure · Nelum